NE 97th Avenue Green Street LID
LID formed by City Council on June 2, 2010.
Design complete.
First phase of construction:
Advertised for bids on April 11, 2011.
Opened bids on April 28, 2011.
Awarded contract to R&R Construction on June 10, 2011.
Paving completed on October 19, 2011.
Construction substantially complete on November 10, 2011.
Second phase of construction:
Advertised for bids on June 20, 2012.
Opened bids on July 12, 2012.
Awarded contract to Kodiak Pacific Construction on September 12, 2012.
Construction scheduled for 11/16/12 through 1/25/13 (schedule provided by contractor as of 10/31/12; subject to change due to weather, utility relocation or other factors).
Upcoming construction schedule provided by the contractor as of 1/09/13 (weather permitting and subject to change by contractor):
Week of January 7, 2013
No activity
Week of January 14, 2013
1) Install NE 97th Avenue conduits for lights
Week of January 21, 2013
1) Install NE 97th Avenue conduits for lights
Week of January 28, 2013
1) Excavate for NE Everett Place curb and sidewalk
2) Excavate for NE Everett Place roadway
3) Base rock NE Everett Place roadway and curb area
4) Pour NE Everett Place curb
Week of February 4, 2013
1) Install NE 97th Avenue street light bases
2) Form and pour NE Everett Place stormwater facility
Week of February 11, 2013
1) Backfill NE Everett Place curb
2) Prepare to construct and pour NE Everett Place sidewalks
3) Prepare to construct and pour NE Everett Place driveways
Week of February 18, 2013
1) Pour NE Everett Place sidewalks
2) Pour NE Everett Place driveways
3) Install NE Everett Place topsoil
4) Complete NE Everett Place base rock
5) Pave base lift of NE Everett Place
6) Pave top lift of NE Everett Place
7) Install NE Everett Place street lights and pull wire
Week of February 25, 2013
1) Install signs
2) Complete NE Everett Place stormwater facility
3) Complete topsoil and seeding
Streets include:
- NE 97th Avenue from Glisan Street to Davis Street
Phase I Construction Plans (24 MB *.pdf file)
Street and westside sidewalk substantially completed Fall 2011
Swale vegetation work not adjacent to I-205 Multiuse Path to be completed in Spring 2013
Eastside sidewalk will be constructed Fall 2012 following conduit work
Street trees to be installed Spring 2013
- Interstate 205 Multiuse Path adjacent to NE 97th Avenue
Concrete and drainage work substantially completed Fall 2011
Swale vegetation work adjacent to I-205 Multiuse Path to be completed in Winter 2013
Street trees adjacent to I-205 Multiuse Path to be installed Spring 2013
- NE Everett Place from NE 97th Avenue to NE 99th Avenue
Phase II Construction Plans (25 MB *.pdf file)
To be constructed Fall 2012 - Winter 2013
Property owners are funding this local improvement district with partial funding from the Portland Development Commission (tax increment funds from the Gateway Urban Renewal Area) and the Bureau of Environmental Services' Watershed Investment Fund and 1% for Green fund. The Oregon Department of Transportation is funding renovations to the Interstate 205 Multiuse Path.
If you have any questions this project, please contact Andrew Aebi, Local Improvement District Administrator and Project Manager, at 503-823-5648 or via e-mail at andrew.aebi@portlandoregon.gov.
If you have any questions about the Gateway Urban Renewal Area, please contact Sue Lewis at 503-823-3331 or via e-mail at lewiss@pdc.us.
If you have any questions about the Watershed Investment Fund or 1% for Green, please contact Emily Hauth at 503-823-7378 or via e-mail at emily.hauth@portlandoregon.gov.
If you have any questions about the Interstate 205 Multiuse Path, please contact Shelli Romero at 503-731-8231 or via e-mail at shelli.romero@state.or.us