NE Alberta Street Phase I LID
LID formed by City Council on September 8, 2010.
Links to plans and bid information:
100% Plans as of July 2, 2012 (28.3MB *.pdf file)
Advertised for bids on July 2, 2012.
Bid # 14620 July 2, 2012 (20.8MB *.pdf file)
Bids opened on July 19, 2012.
Contract executed on September 13, 2012.
Paving completed on April 10, 2013.
Remaining street trees and swale vegetation will be planted in May 2013; no more schedule updates will be provided.
Final assessment pending; anticipated for Fall 2013; check Council calendar.
Streets include:
- NE Alberta Street from 76th Avenue to 79th Avenue
- NE 78th Avenue from 300 feet north of Wygant Street to Alberta Street
Property owners are funding this local improvement district with partial funding from the Portland Bureau of Transportation for overhead costs.
If you have any questions this project, please contact Andrew Aebi, Local Improvement District Administrator and Project Manager, at 503-823-5648 or via e-mail at andrew.aebi@portlandoregon.gov.