Division Streetscape + Reconstruction
SE Division Streetscape between 6th + 39th Avenues
Read More…
Phone: 503-823-5185
Fax: 503-823-7576
1120 SW Fifth Ave, Suite 800, Portland, OR 97204
The Transportation Bureau manages a wide array of projects that improve Portland's streets. Planning for these projects may be done years in advance for major projects or spur-of-the-moment for emergencies and minor repairs. Regardless, PBOT is constantly working to keep our streets in the best condition possible with the local funds we have and the state and national funds we seek.
Below is a table of significant projects that are currently funded and scheduled. For a list of unfunded projects for Portland, visit the Transportation System Plan. We are not including minor repairs because there are too many done every day to efficiently record in a table.
Updated: April 22, 2013 (Schedule subject to change due to weather, budget and other unforeseen events)
| STREET | WHAT'S HAPPENING | LOCATION | WHEN | NOTES |
| NORTH PORTLAND | ||||
| Alberta Street, N | Curb extensions | N Alberta St and N Vancouver Ave |
May 2013 |
Safe Routes to School |
| Alberta Street, N | Paving | Intersection east of I-5 | June 3-5, 2013 | 0.143 lane miles |
| Burgard Road, N | Bridge replacement | Over abandoned railroad | August 2012 - May 2014 | Project will replace roadway, build new sewer for stormwater, fill bridge void and allow 9-month soil settlement period between phases. |
| Edison Street, N | Permit job -public street improvement | N Edison St and N Baltimore St | COMPLETED | |
| Hayden Island Drive, N | Permit job - public street improvement | N Hayden Island Dr and N Parker Ave |
COMPLETED |
|
| Macrum Avenue, N | Permit job - public street improvement | N Macrum Ave and N Ashton St | January 2013 - June 2013 | |
| Portland Road, N | Paving | 64m north of structure to N Marine Dr | COMPLETED | 1.94 lane miles |
| Vancouver Way, N | Paving | NE 3rd Ave to N Marine Dr |
April 8-24, 2013 |
3.457 lane miles |
| Willis Boulevard, N | Curb extensions and pedestrian island | N Willis Blvd and N Herefor St | May 2013 | Safe Routes to School |
| Willis Boulevard, N | Pedestrian island | N Willis Blvd and N Hodge St | May 2013 | Safe Routes to School |
| NORTHEAST PORTLAND | ||||
| 11th Avenue and Lombard Street, NE | Signals | NE 11th Ave and NE Lombard St | COMPLETED | |
| 12th Avenue and Glisan Street, NE | Signals and curb extension | NE 12th Ave near NE Glisan St | January-March 2013 | Rapid flash beacon and curb extension |
| 13th Avenue, NE | Permit job - frontage improvements | NE 13th Ave at NE Marine Dr and NE Faloma Rd |
COMPLETED |
|
| 21st Avenue, NE | Bridge rehabilitation | NE 21st Ave Bridge over Columbia Slough | COMPLETED | |
| 28th Avenue, NE | Paving | NE Glisan St to E Burnside St |
April 19-25, 2013 |
0.728 lane miles |
| 33rd Avenue, NE | Permit job - frontage improvements | NE Schuyler St to NE Broadway |
COMPLETED |
|
| 42nd Avenue, NE | Bridge resurfacing | NE 42nd Ave bridge over Portland Highway | COMPLETED | |
| 82nd Avenue, NE | Detection and data collection | Various locations | COMPLETED | Installed sample loops to improve data collection for traffic operations improvements |
| 82nd Avenue, NE | Traffic signal reconstruction | NE Prescott St | Spring 2013 | Waiting for utility company to move pole |
| 97th Avenue, NE | Property owner funded LID street construction with additional funding from BES, ODOT and PDC | NE Everett Pl: NE 97th Ave to NE 99th Ave | COMPLETED | Local improvement district |
| 102nd Avenue, NE | Sidewalk infill | NE Weidler to I-84 | ||
| 122nd Avenue, NE | Paving | NE Holladay St to NE Halsey St | COMPLETED | 1.31 lane miles |
| 122nd Avenue, NE | Paving | Intersection at NE Shaver St | May 29-31, 2013 |
0.367 lane miles |
| 136th Avenue, NE | Property owner funded LID street construction | 364 ft north of NE Prescott Ct to NE Whitaker Way | COMPLETED |
Local improvement district |
| Alberta Street, NE | Property owner funded LID street construction | NE 76th Ave to NE 79th Ave | COMPLETED | Local improvement district |
| Brazee Street, NE | Curb ramps | NE Brazee St and NE 132nd Ave | May 2013 | Safe Routes to School |
| Columbia Boulevard, NE | Bridge resurfacing | NE Columbia Blvd over NE 33rd Dr | COMPLETED | |
| Cully Boulevard, NE | Paving |
NE Prescott St to NE Failing St then on NE 57th Ave to NE Fremont St |
April 26-May 2, 2013 |
2.889 lane miles |
| Halsey Street, NE | Paving | NE 84th Ave to NE 92nd Ave |
May 3-10, 2013 |
1.848 lane miles |
| Marine Drive, NE | Paving | Weather Station to 1,500 ft west of I-205 | COMPLETED | 8.94 lane miles |
| Martin Luther King Jr. Boulevard, NE | Permit job - frontage improvements | NE Martin Luther King Jr. Blvd & NE Sumner St | COMPLETED | |
| Martin Luther King Jr. Boulevard, NE | Rapid flash beacon and audible push buttons | NE Bryant St | Spring 2013 | |
| Multnomah Street, NE | Paving | NE 1st Ave to NE Martin Luther King Jr. Blvd | COMPLETED | 0.748 lane miles street repaving plus new lane striping, signal timing adjustments, traffic delineators and potted planters |
| Multnomah Street, NE | Permit job - public street improvement | NE Multnomah St and NE 1st Ave | COMPLETED | |
| Prescott Street, NE | Sidewalk infill | NE 105th Ave to NE 116th Ave | Project bid opening May 2013 | Sidewalk infill on south side of Prescott. Adding curb and paving shoulder area/parking lane. |
| Sandy Boulevard, NE | Capital improvement paving | NE 47th Ave to NE 82nd Ave | COMPLETED | Street repaving plus curb ramps, traffic signals, stormwater planters and new sewers |
| Sandy Boulevard, NE | Permit job - public street improvements | NE Sandy Blvd and NE 41st Ave |
September 2012 - June 2013 |
|
| SOUTHEAST PORTLAND | ||||
| 3rd Avenue, SE | Permit job - public street improvements | SE 3rd Ave and SE Alder St |
October 2012 - June 2013 |
|
| 3rd Avenue, SE | Permit job - public street improvements | SE 3rd Ave and SE Clay St |
September 2012 - June 2013 |
|
| 3rd Avenue, SE | Permit job - public street improvements | SE 3rd Ave and SE Market St |
September 2012 - June 2013 |
|
| 17th Avenue, SE | Paving | SE Bybee Blvd to SE Claybourne St | COMPLETED | 0.375 lane miles |
| 24th Avenue to 26th Avenue, SE | Permit job - public street improvements | SE Stark St to SE Oak St |
COMPLETED |
|
| 37th Avenue, SE | Permit job - public street improvements | SE Division St to SE Caruthers St |
September 2012 - June 2013 |
|
| 38th Avenue, SE | Permit job - public street improvements | SE 38th Ave and SE Belmont St |
September 2012 - July 2013 |
|
| 82nd Avenue and Bybee Boulevard, SE | Property owner funded LID street construction | SE Bybee Blvd to 168 ft south of Cooper Street | COMPLETED | Local improvement district |
| 85th Avenue, SE | Permit job - public pathway improvements | SE 85th Ave and SE 86th Ave pedestrian connection south of SE Pardee St |
September 2012 - July 2013 |
|
| 93rd Avenue, SE | Permit job - frontage improvements | SE 93rd Ave and SE Woodstock Blvd | January-June 2013 | |
| 99th Avenue, SE | Permit job - public street improvements | SE 99th Ave and SE 100th Ave at SE Bush St |
November 2012 - July 2013 |
|
| 106th Avenue, SE | Permit job - public street improvements | SE 106th Ave and SE Stark St |
September 2012 - July 2013 |
|
| 109th Avenue, SE | Permit job - public street improvements | SE 109th Ave and SE Clinton St |
October 2012 - July 2013 |
|
| 118th Avenue, SE | Property owner funded LID street construction with additional funding from PDC | SE Pardee St to SE Liebe St | COMPLETED, except for speed bumps | Local improvement district |
| 122nd Avenue, SE | Bridge rehabilitation | SE 122nd Ave Bridge over Johnson Creek | COMPLETED | Bridge deck rehabilitation and repaving |
| 122nd Avenue, SE | Permit job - public sidewalk improvements | SE 122nd Ave and SE Stark St |
September 2012 - July 2013 |
|
| 162nd Avenue, SE | Sidewalk infill | SE Powell Blvd to SE Salmon St | October 2012 - May 2013 | |
| 174th Avenue, SE | Permit job - public street improvements | SE 174th Ave and SE Grant St | February-August 2013 | |
| Ankeny Street, SE and Burnside Street | Permit job - public street improvements | SE 12th Ave to SE 13th Ave |
COMPLETED |
|
| Bybee Boulevard, SE | Property owner funded LID street constuction | SE 82nd Ave to 37 ft east of SE 81st Pl | COMPLETED | Local improvement district |
| Cesar E Chavez Boulevard, SE | Bike detection at traffic signal | SE 39th Ave | December 2012 | New bike detection technology for westbound bicyclists at existing traffic signal |
| Division Street, SE | Capital improvement street reconstruction | SE 11th Ave to SE Cesar Chavez Blvd | January 2013 - Fall 2013 | Streetscape project includes street reconstruction and paving plus street trees, bioswales, curb extensions, crosswalks, street lights, traffic signals, sewers and public art |
| Division Street, SE | Permit job - public sidewalk improvements | SE Division St and SE 148th Ave | COMPLETED | |
| Division Street, SE | Rapid flash beacon and audible push buttons | Bike/pedestrian crossing west of I-205 | COMPLETED | |
| Division Street, SE | Sidewalk infill | SE 148th Ave to SE 175th Ave | ||
| Division Street, SE | Traffic signal reconstruction | SE 26th Ave | Winter-Spring 2013 | |
| Ellis Street, SE | Permit job - public street improvements | SE Ellis St and SE 87th Ct | January-July 2013 | |
| Foster Road, SE | Rapid flash beacon and audible push buttons | SE Cora St | COMPLETED | |
| Foster Road-Woodstock Boulevard, SE | Capital improvement streetscape | Various streets | October 2012 - May 2013 | Streetscape project includes street reconstruction and paving plus sidewalk reconstruction, street lights, street trees, intersection and crosswalk improvements, new traffic signal and on-street parking |
| Harold Street, SE | Curb ramps | SE Harold St and SE 97th Ave | March 2013 | Safe Routes to School |
| Hawthorne Boulevard, SE | Detection for southbound bicycle traffic | SE Hawthorne Blvd and SE 16th Ave | March 2013 | |
| Holgate Boulevard, SE | Permit job - frontage improvements | SE 122nd Ave and SE Holgate Blvd |
January-July 2013 |
|
| Lincoln Street, SE | Curb ramps | SE Lincoln St and SE 57th Ave | May 2013 | Safe Routes to School |
| Market Street, SE | Curb ramps | SE Market St and SE 117th Ave | May 2013 | Safe Routes to School |
| Powell Boulevard, SE | Street lighting upgrade | SE 52nd Ave to SE 82nd Ave | COMPLETED | LED streetlighting pilot project |
| Rhine Street, SE | Permit job - public sidewalk improvements | SE 82nd Ave and SE Rhine St |
COMPLETED |
|
| Stark Street, SE | Rapid flash beacon and audible push buttons | SE 126th Ave | COMPLETED | |
| Stark Street, SE | Sidewalk infill | SE 126th Ave to SE 162nd Ave | October 2012 - May 2013 |
Sidewalk infill on both sides of Stark. Crossing improvements and rectangular rapid flash beacons at SE 133rd and 160th. |
| Steele Street, SE | Curb ramps | SE Steele St and SE 96th Ave | May 2013 | Safe Routes to School |
| Stephens Street, SE | Curb ramps | SE Stephens St and SE 122nd Ave | May 2013 | Safe Routes to School |
| Tacoma Street, SE | Vehicle detection equipment | SE 13th Ave | December 2012 | Vehicle detection improvement in left turn lanes |
| Washington Street, SE | Paving | SE 82nd Ave to SE 90th Ave | COMPLETED | 1.91 lane miles |
| NORTHWEST PORTLAND | ||||
| 14th Avenue, NW | Permit job - public street improvements | NW 14th Ave and NW Everett St, NE corner | COMPLETED | |
| 16th Avenue, NW | Paving | NW Lovejoy St to NW Thurman St | COMPLETED | 1.12 lane miles |
| 23rd Avenue, NW | Permit job - frontage improvements | NW 23rd Ave and NW Raleigh St |
May 2012 - July 2013 |
|
| Burnside Road, W | Paving | NW Skyline Blvd to the tunnel | COMPLETED | 0.74 lane miles |
| Everett Street, NW | Permit job - frontage improvements | NW Everett St and NW 12th Ave |
COMPLETED |
|
| Flanders Street, NW | Permit job - frontage improvements | NW Flanders St and NW 14th Ave, NW corner | COMPLETED | |
| Glisan Street, NW | Permit job - public street improvements | NW Glisan St and NW 3rd Ave |
COMPLETED |
|
| Lovejoy Street, NW | Permit job - public street improvements | NE Lovejoy St east of NW 23rd Ave |
April 2012 - July 2013 |
|
| Nicolai Street, NW | Permit job - public street improvements | NW Nicolai St and NW Yeon Ave |
October 2012 - June 2013 |
|
| Overton Street, NW | Permit job - public street improvements | NW Overton St and NW 11th Ave |
April 2012 - July 2013 |
|
| Savier Street, NW | Permit job - public street improvements | NW Savier St and NW 23rd Ave |
COMPLETED |
|
| Thurman Street, NW | Paving | NW Gordon St to NW 31st Ave | COMPLETED | 1.32 lane miles |
| Thurman Street, NW | Paving | NW Thurman St Bridge | June 6-19, 2013 | 0.19 lane miles |
| SOUTHWEST PORTLAND | ||||
| 3rd Avenue, SW | Permit job - public street improvements | SW 2nd Ave and SW 3rd Ave between SW Madison St and SW Jefferson St |
June 2012 - July 2013 |
|
| 5th Avenue, SW | Paving | SW Broadway to SW Sheridan St | COMPLETED | 0.4 lane miles |
| 10th Avenue, SW | Permit job - public street improvements | SW 9th Ave and SW 10th Ave between SW Morrison St and SW Alder St |
October 2012 - July 2013 |
|
| 11th Avenue, SW | Capital improvement paving | SW Curry St to SW Gibbs St | Paving scheduled for June 2013 | |
| 11th Avenue, SW | Sidewalks | SW Curry St to SW Gibbs St | COMPLETED on east side of street | West side of street several years out |
| 12th Avenue, SW | Permit job - frontage improvements | SW 12th Ave and SW Whitaker St |
October 2012 - July 2013 |
|
| 58th Avenue, SW | Permit job - public street improvements | SW 58th Ave and SW Montgomery St |
January-August 2013 |
|
| 63rd Avenue, SW | Permit job - public street improvements | SW 63rd Ave and SW Vermont St |
May-December 2013 |
|
| Barbur Boulevard, SW | Paving | SW Sheridan St to SW Viewpoint Ter | COMPLETED | 3.39 lane miles |
| Beaverton Hillsdale Highway, SW | Rapid flash beacon and audible push buttons | SW 62nd Ave | November-December 2012 | |
| Broadway, SW | Paving | I-405 to SW 5th Ave |
June 22-23, 2013 |
0.574 lane miles |
| Capitol Highway, SW | Bridge rehabilitation | Over Bertha Blvd | COMPLETED | Bridge rail restoration |
| Capitol Highway, SW | Bridge rehabilitation | Over Bertha Blvd | In progress | Bridge concrete substructure repair |
| Capitol Highway, SW | Permit job - public street improvements | SW Capitol Hwy and SW Taylors Ferry Rd |
COMPLETED |
|
| Capitol Highway, SW | Traffic signal improvements | SW Vermont St | December 2012 | Traffic signal span upgrade to improve reliability in inclement weather |
| Huber Street, SW | Sidewalk infill | SW 35th Ave to SW 43rd Ave | July 2013 | Project just advertised; construction should start this summer |
| Lowell Street, SW | Permit job - frontage improvements | SW Bond Ave to SW Moody Ave, Block 49 | COMPLETED | |
| Macadam Avenue, SW | Permit job - public street improvements | SW Bond Ave to SW Moody Ave |
COMPLETED |
|
| Macadam Avenue, SW | Traffic signal improvements | Various locations | September 2012 - April 2013 | Installing traffic signal pre-emption |
| Macadam Avenue, SW | Traffic signal improvements | SW Miles St to SW Bancroft St | Winter 2012-2013 | Improving progression between traffic signals |
| Moody, SW, Phase II: Curry Closure | Safety improvement | SW Curry St at SW Macadam Ave | Phase I August 2013 (signs); Phase II October 2013 (traffic median and signal) | Phase II waiting until TriMet work at SW Porter Street is complete |
| Naito Parkway, SW | Capital improvement street reconstruction | SW Jefferson St to I-405 | FY 2013-14 | |
| Pine Street, SW | Paving | SW 4th Ave to SW Naito Pkwy | April 1-5, 2013 | 0.59 lane miles |
| Sam Jackson Park Road, SW | Traffic signal pole and cabinet relocation | SW Sam Jackson Park Rd and SW Terwilliger Blvd | March 2013 |
|
| Sheridan Street, SW | Paving | SW 5th Ave to SW Barbur Blvd | COMPLETED |
0.23 lane miles |
| Spring Garden Street, SW | Sidewalk infill | SW 19th Ave and SW 22nd Ave | June 2013 |
|
| Stark Street, SW | Paving | SW 10th Ave to SW Broadway | June 20-26, 2013 |
0.39 lane miles |
| Sunset Boulevard, SW | Sidewalk infill | SW Dewitt St to SW 18th Ave | June 2013 |
|
| Vermont / Illinois Neighborhood Greenway, SW | Sidewalk infill and neighborhood greenway improvements | SW 30th Ave to SW 37th Ave (sidewalk infill); SW Terwilliger Blvd at SW Chesnut St and at SW 7th Ave; SW Vermont St at SW Idaho Dr | Bid May 2013 |
Sidewalk infill only on south side of Vermont. Three other locations are spot improvements for stormwater management and crossing safety. |