Construction Schedule
Construction is anticipated to start in mid-October with substantial completion by the end of May, 2013.
The general schedule of construction activity by location is as follows:
- SE 91st Ave/Foster: mid Oct to mid Nov, '12
- SE 92nd Ave/ Reedway to Woodstock: mid Nov to mid March, '13
- SE Ramona St: Dec to mid Jan, '13
- SE Foster Rd/ northside: Jan to March, '13
- SE Foster Rd/south side: March, '13
- SE Woodstock Blvd: April, '13