What does it mean when the engineer says we need to "take in" your project?

 

Typically we try to limit our over the counter review time to about 15 or 20 minutes. This allows us to see all of our structural customers with the least amount of wait time. If your project requires an in depth review, we ‘take it in' and assign it to a specific engineer. Once your project is taken in, you can check the status of your permit online at www.portlandoregon.gov/bds or request the status by fax at 503.823.7000. Please be ready with your IVR number. The City's turnaround goals for reviewing projects that have been taken in are:

 

Structural Engineering Group

Permit Type

Working Days to 1st Review

Working Days to Recheck

Residential Alterations

7

3

Commercial Alterations

< $200,000.00 and

does not include a seismic upgrade


10

 


5

 

Commercial Alterations

> $200,000.00 or

includes a seismic upgrade

20

5

RS Additions

15

5

CO Additions

20

5

RS New Construction

15

5

CO New Construction

20

5

Process Managed or projects in Major Projects Group

Determined in consultation with the applicant

Determined in consultation with the applicant

 

"Working Days to 1st Review" is defined as the number of business days following intake. Day 1 would be the next business day after intake. "Working Days to Recheck" is defined as the number of business days following the date that the bureau is notified that recheck comments have been received.