Vernon-Sabin-Alameda Sewer Project

Environmental Services will start work in spring 2013 on the first phase of a project to repair deteriorating sewer pipes in the Vernon, Sabin, and Alameda neighborhoods. Sewers in these neighborhoods are between 90 to 100 years old.

This project will repair about 9,400 feet of sewer and about 5,100 feet of lateral pipes to connect individual properties to the public sewer. The city's contractor will use both open trench construction and cured-in-place pipe lining to repair sewers.

There will be two construction phases (please see maps and schedules below).

Tree Trimming for Phase 1

To prepare for the large construction equipment the contractor will use on this project, Portland Parks & Recreation arborists will trim street trees and low branches of private trees. The trimming will reduce the possibility of large equipment damaging trees and will help ensure public safety.

Portland City Code requires property owners to maintain street trees adjacent to their property and keep limbs at least 7.5 feet above sidewalks and 11 feet above streets. But all tree trimming for this project will be done at the city's expense.

Phase 1 Schedule

  • Phase 1 work will continue for one year.
  • Construction hours are 7:00 a.m. to 6:00 p.m. Monday through Friday. The contractor may work the same hours on Saturday if needed.
  • Construction hours on NE Killingsworth, NE Prescott and NE Alberta streets are 9:00 a.m. to 3:00 p.m.

What to Expect During Construction

  • Construction will create noise, vibration and dust and disrupt normal neighborhood activity.
  • Parking will be prohibited in the work zone.
  • Traffic congestion in the area will increase and you may experience delays in getting to your destination.
  • There may be periods of inactivity between construction phases.
  • A city construction inspector will be on-site during work hours. If you have an immediate need during construction, the on-site inspector may be able to assist you.
  • Let us know if you have concerns such as business operations, disability issues or medical or business deliveries.

For More Information

For information about phase one of the Vernon-Sabin-Alameda project, contact Becky Tillington at 503-823-2827. To receive occasional email updates for phase one of the project, email Becky Tillington with “VSA Phase I” in the subject line.

For information about phase 2 of the Vernon-Sabin-Alameda project, contact Cheryl Kuck at 503-823-7898. To receive occasional email updates for phase two of the project, email Cheryl Kuck with “VSA Phase 2” in the subject line.

 

Phase One construction map

Phase I Schedule

Construction starts in spring 2013 and will take about one year to complete.

map of Vernon Sabin Alameda sewer project

Phase 2 Schedule

Construction will start in late 2013 and will take about one year to complete. For information about