Sellwood-Moreland Sewer Repair Project

Environmental Services continues to repair or replace about 25,000 feet of public sewer pipes in the Sellwood-Moreland neighborhood that are between 80 and 100 years old and deteriorating due to age. This project will help protect the public and the environment by reducing the possibility of costly breaks, leaks, blockages and sewage releases to homes, businesses and streets.

Sellwood-Moreland Sewer Project map

Developments of Note

Over the past few weeks, crews have been working to complete sewer repairs on five blocks around Llewellyn Elementary School.  All the work on the blocks closest to the school was completed before school started.  We appreciate your cooperation and patience with any school-commute inconvenience our work on SE Martins may have caused.  After several more days of surface restoration, the work around Llewellyn should be complete. .

Construction Schedule

 

The anticipated construction schedule for the next three weeks is subject to change due to underground conditions, weather, subcontractor schedules and availability of materials.

  • Over the next several weeks, crews plan to pave the following streets:
    • SE 11th between Bidwell and Nehalem
    • SE Milwaukie between Lambert and Bidwell
    • SE Martins between 13th and Milwaukie
  • Sometime in the next three weeks, crews plan to pour manhole channels and stormdrains in various locations around the neighborhood

Week of August 31:

  • SE Nehalem Street (between 8th and 11th) – open trench construction to repair mainline (starting between 8th and 9th, and progressing to the stretch between 9th and 11th)
  • SE Glenwood (between 14th and 16th) – prepare for and conduct pipe bursting (bursting planned for Wednesday), install manhole and new branches to connect individual properties to mainline
  • SE 16th Ave (between Glenwood and Bybee) – prepare for pipe bursting

Week of September 7:

  • SE Nehalem Street (between 9th and 11th) – open trench construction to repair mainline
  • SE 16th Avenue (between Glenwood and Bybee) – conduct pipe bursting, install manhole and new branches to connect individual properties to mainline
  • SE 18th Avenue (just south of Claybourne) – prepare for pipe bursting

Week of September 14:

  • Pour manhole channels and stormdrains in various locations around the neighborhood
  • SE Nehalem Street (between 9th and 11th) - install branches to individual properties
  • SE 18th Avenue (just south of Claybourne) – conduct pipe bursting; install manhole and new branches to connect individual properties to mainline

For More Information

To report concerns during night work, please call the on-site hotline at 503-823-1257. You may also call the Portland Noise Control Office at 503-823-7350. If you have other questions about the project, contact Amy Higgs at 503-975-7073. To receive regular email updates about this project, please send an email to Amy with “Sellwood-Moreland” in the subject line.