Skip to Main Content View Text-Only

Environmental Services

working for clean rivers

Phone: 503-823-7740

Fax: 503-823-6995

1120 SW 5th Avenue, Room 1000, Portland, OR 97204

More Contact Info

Kenton Sewer Repair Project

Kenton Sewer Repair Project Construction Update: November 21, 2014

Environmental Services has begun construction on the Kenton Sewer Repair Project. This project will replace about 7,000 feet of public sewer pipes that are between 80 and 90 years old and failing due to age. The work will include repairing or replacing about 2,500 feet of existing service laterals that connect houses and businesses from the curb to the public sewer in the street. This project will increase sewer capacity and reduce the risks of street flooding and sewage releases to homes, businesses and streets.

WHAT WE’VE HEARD FROM YOU
Neighbors have noticed that our equipment occasionally remains on a block for several days after it appears that construction has been completed.  In these situations, we are likely planning to return to the block to construct a lateral to a property, or to complete another task that requires a separate crew and specialized equipment.  To ensure the most effective use of ratepayer money, once several blocks are ready for this work, we will send out a crew to repair multiple laterals at once.

CONSTRUCTION SCHEDULE

Below is the anticipated construction schedule for the next two weeks.  This schedule is subject to change due to a variety of factors, including underground conditions, weather, subcontractor schedules and availability of materials.  As the contractor completes construction on each street, work crews apply a temporary asphalt patch. They will return at a later date to apply permanent paving.  In recognition of the Thanksgiving holiday, crews will not be working November 27 and 28th

Week of November 24:

  • N Brandon Ave (between Russett and Lombard) – underground video inspection
  • N Watt St (between Brandon and Delaware) – underground video inspection
  • N Schofield (between Brandon and Delaware) - underground video inspection
  • N. Baldwin (between Minnesota and Interstate) – finish replacement of combined sewer/stormwater line and manholes at Montana.
  • N. Farragut (between Montana and Minnesota) –replacement of single lateral pipe to property

Week of December 1:

  • N. Kilpatrick St (between Brandon and Delaware) - underground video inspection
  • N Brandon Spot Repair – open trench spot repair just north of Farragut St (in front of 2135 N Farragut)
  • N Brandon Ave (between Russett and Lombard) – begin work on open trench main line, repair manholes and construct stormwater inlet on SE corner of Brandon and Farragut.
  • N. Baldwin (between Minnesota and Interstate) – replace laterals between Minnesota and Montana

Note: We will NOT be conducting work on November 27th or 28th in recognition of the Thanksgiving holiday. 

Construction Methods

The city will use a combination of open trench construction, cured-in-place-pipe lining, and pipe bursting. Click here for details about each construction method.

Night Work at Several Locations

The Portland Noise Control Office granted Environmental Services a noise variance for nighttime construction at several locations in this project (see map below).

A city inspector will be on-site during this night work. To report concerns during night work, please call the on-site hotline at 503-823-8458. You may also call the Portland Noise Control Office at 503-823-7350 or email noise@portlandoregon.gov.

N Interstate Avenue and N Russet Street

Construction in the intersection of N Interstate Avenue and N Russet Street will occur from 10:00 p.m. to 6:00 a.m. Monday through Saturday and should take no more than five days to complete. Businesses and residents in the construction area will be notified in advance of this night work.

The city’s contractor will excavate a trench to replace the public sewer pipe. The contractor will use heavy equipment to excavate and restore the pavement, and temporary lighting for the work area at night. The southbound travel lane of N Interstate Avenue will be closed and traffic re-routed during construction hours.

Cured-in-place Pipe Lining Locations

The contractor will use cured-in-place pipe lining (CIPP) to repair several sewers. Work crews may install lining at night at some locations because of the size of the pipe. Work at each location should take no more than a few days. People who live and work near a CIPP repair project can sometimes smell a chemical odor during pipe-lining. The odor is from the chemical styrene, which is in the resin liner installed inside the pipe. The odor dissipates quickly once the installation process is complete. The amount of airborne styrene the repair process produces is not a human health risk. Click here for more details about CIPP.

Project Area Map

The map below shows the location of pipes we will repair or replace. There may be temporary traffic controls, construction signage or increased traffic volume and parking on nearby streets.

Kenton Sewer Repair Map

What to Expect during Construction

  • Construction creates noise, vibration and dust and disrupts normal neighborhood activity.
  • Typical construction hours will be 7:00 a.m. to 6:00 p.m. Monday through Friday. If needed, the contractor may work the same hours on Saturday. The contractor will work at night to complete the cured-in-place pipe lining on larger pipes in several locations (see map). One location will require nighttime work to complete the open trench sewer repair. To minimize daytime traffic disturbance on N Interstate Avenue, sewer construction in the intersection of N Russet Street and N Interstate Avenue will require night work for no more than five days. We will notify residents in advance of night work.
  • Please stay clear of all construction activities and keep children, pets and vehicles out of construction areas.
  • On-street parking in or near the work area may be limited. Please observe no parking signs.
  • Equipment and materials may be stored on nearby streets overnight.
  • The contractor will maintain local access on streets, but you should expect delays. In some cases, construction activities may impact normal use of your driveway.
  • Sewer construction generally occurs in the street. However, in a few areas the contractor will have to cut into sidewalks and driveway edges then restore the areas. Construction may also affect the planting strip, the area between the curb and sidewalk. We will notify property owners where this may occur.
  • During construction, the city’s contractor will use by-pass pumps to maintain sewer service. If a short, temporary sewer service shut-off is necessary to relocate a line, the contractor will notify property owners in advance.
  • Construction near an individual property could last a few weeks. This may seem longer where the work extends on the same street for a block or more. Sewer construction has many phases, and there may be periods of inactivity between construction phases at each site.
  • A city inspector will be on-site during work hours and may be able to assist you with concerns. Inspectors wear a hard hat and a safety vest with “City of Portland” on the back.

For More Information

To report concerns during night work, please call the on-site hotline at 503-823-8458. You may also call Portland Noise Control Office at 503-823-7350 or email noise@portlandoregon.gov. If you have other questions about the project, contact Amy Higgs at 503-975-7073 or amy@loisdcohen.com. To receive regular email updates about this project, please send an email to Amy with “Kenton” in the subject line.