Grant Park Sewer Repair

July 3, 2014

The Grant Park Sewer Repair Project will replace or repair about 11,500 feet of public sewer pipes that are between 89 and 104 years old and failing due to age. This project will increase sewer capacity and reduce the risks of street flooding and sewage releases to homes, businesses and streets. Construction should be complete by March 2015.

Construction Schedule

  • Overnight sewer construction that begins Monday night, July 7 will close traffic lanes around the intersection of NE Broadway and NE 33rd Avenue.
  • Work hours will be 8:00 p.m. to 6:00 a.m. Monday through Saturday and construction at NE Broadway and NE 33rd  will last for about two weeks.
  • Construction at that intersectionwill detour traffic to I-84 westbound and to 33rd Avenue southbound when all southbound travel lanes on 33rd are closed at Broadway.
  • Nighttime construction will enable the contractor to complete the work as quickly and as safely as possible, avoid weeks of disruption at this intersection, and minimize impacts on 33rd, Broadway, I-84 and neighborhood streets.
  • After night work is complete at this intersection, sewer construction will occur during the day along NE Broadway.
  • Construction hours throughout the rest of the summer will be Monday through Saturday from 7:00 a.m. to 6:00 p.m.
  • The work zone will move west from NE 33rd Avenue toward NE 27th Avenue.
  • Motorists should expect delays.
  • TriMet will temporarily relocate bus stops along eastbound NE Broadway as needed during the summer.

Upcoming Work

  • NE Broadway – After repairs are completed at the intersection with 33rd Avenue, work on NE Broadway will move west toward NE 27th Avenue, with daytime work hours from 7:00 a.m. to 6:00 p.m. Monday through Saturday. The work will delay traffic on NE Broadway, but there will be one lane in each direction at all times and two lanes in each direction by the afternoon commute. Work on NE Broadway should be completed in September. There will be intersection closures at NE 32nd, 30th and 28th avenues. The closures will not occur at the same time. Watch for signs.

  • The contractor is scheduling work on residential streets, including additional lining and restoration work on US Grant Place and NE Hancock Street.

Map of construciton phases on Broadway

 

Grant Park Sewer Repair Project Map 

Phased Construction on NE Broadway

The Grant Park Sewer Repair Project includes sewer repairs along NE Broadway between NE 27th and NE 33rd avenues. Construction will affect businesses, neighbors and traffic between June and September 2014. Crews will excavate a large trench to replace the public sewer pipe that runs along the south side of NE Broadway. The project includes repairing the lateral sewer lines that connect properties on both sides of the street. Construction on NE Broadway will be phased from east to west. Click here for details.

What to Expect During Construction

  • Work hours are 7:00 a.m. to 6:00 p.m. Monday through Friday, but the contractor may schedule work during the same hours on Saturdays. There will be night work on NE Broadway at 33rd Avenue in June.

  • Construction will create noise, vibration and dust and will disrupt normal neighborhood activity.

  • Traffic control signs will be set up, and flaggers may direct traffic on higher-volume streets.

  • On-street parking in or near active work areas is prohibited during construction hours. Please plan to move your vehicle by 7:00 a.m. in work zones.

  • Equipment and materials may be stored on nearby streets overnight.

  • There may be periods of inactivity between construction phases.

  • A city inspector will be on-site during work hours and may be able to assist you with construction concerns. Inspectors typically wear a green safety vest with “City of Portland” across the back and a hard hat.

  • Please stay clear of all construction activities and keep children and pets out of construction areas.

  • You should receive a doorhanger notice a few days before work starts on your street.

Sewer Construction Methods

The city will use a combination of open trench construction, cured-in-place-pipe lining (CIPP), and pipe bursting for this project. The contractor may use more than one construction method in some areas. For example, the contractor may use CIPP on the main public sewer pipe and open trench construction to repair or replace laterals that connect private sewers from the curb to the public sewer in the street.

Open trench installation is done in phases:

  • Saw cut pavement along the width of the trench
  • Remove pavement and existing material
  • Install public sewer pipe in the street
  • Backfill trench with sand or gravel
  • Replace laterals that connect private sewers to the system (from the curb to the street)
  • Restore surface temporarily with an asphalt patch
  • Complete final paving
  • Restore other areas disturbed by construction, such as sidewalks, driveway aprons and planting strips

Cured-in-place-pipe lining (CIPP) doesn’t require digging a trench. Work crews access the sewer from manholes to insert a flexible liner inside the old pipe. Hot water or steam inflates and cures the liner, which gradually hardens to form a rigid, smooth surface that seals cracks and restores the pipe to near-new condition. People who live and work near a CIPP repair project sometimes smell a chemical odor during the pipe-lining work. The odor is from the chemical styrene, which is in the resin liner installed inside the pipe. The odor dissipates quickly once the installation process is complete. The amount of airborne styrene produced is not a human health risk.

Pipe bursting involves digging an access pit and inserting a bursting head into the existing sewer line. The bursting head breaks the old pipe apart and pulls the new pipe into place behind it. Construction crews retrieve the bursting head from a second access pit.

Thank you in advance for your cooperation during this project. Please let us know if you have concerns such as business operations, disability issues, or medical or business deliveries. As always, we’ll strive to provide quick response to your concerns, minimal disruption near your residence or business, and open and clear communication with you throughout the project.

For More Information

Contact Kristen Kibler with JLA Public Involvement  at 503-235-5881, extension 106, if you have concerns, such as maintaining driveway access, business operations, or medical deliveries, during construction.

Email Kristen  with "Grant Park" in the subject line to receive project updates by email. During construction, we will be sending regular email updates to keep you posted about the schedulem, construction activities, possible traffic detours and delays, parking restrictions and other impacts.