SE Division Street Paving Underway

SE Division Street between SE 26th Avenue and Cesar Chavez Boulevard

Paving for the Division Streetscape Project began on June 14. After paving is completed, the city's contractor will apply permanent striping.

The Portland Noise Office granted Environmental Services a noise variance that allows paving work on weekdays and weekends and some night work.

The contractor is paving Division in sections starting on the west end of SE Division and moving east to Cesar Chavez. There may be short periods during grinding and paving work when driveway access from SE Division will be limited. Property owners will be notified before this work occurs. The contractor will maintain local access to properties in the work area.

West bound traffic will be maintained on SE Division during paving. Eastbound traffic will be temporarily detoured each day during working hours, and reopened at 6:00 p.m. each evening. Please obey all flaggers and follow signed detour routes when traveling on SE Division. 

Paving in Sections

The contractor is paving Division in sections:

  • Section 1: between SE 11th and 12th avenues – Completed, stripping to be completed this summer. 
  • Section 2: between SE 12th and Ladd avenues – Completed, stripping to be completed this summer.
  • Section 3: between Ladd and 26th avenues – Completed, stripping to be completed this summer.

  • Section 4: between SE 26th and 34th avenues – Tentatively scheduled to begin the week of September 1.

  • Section 5: between SE 34th Avenue and Cesar Chavez Boulevard – Grinding and paving scheduled to begin the week of August 18.  

Work for Sections 4 and 5 will occur during regular work hours, 7:00 a.m. to 6:00 p.m., Monday through Friday, but the contractor may schedule work during the same hours on Saturday.

Temporary striping will be applied and stay in place until sections of paving are completed, and then permanent striping will be applied. Permanent striping will be applied during weekdays (Monday through Friday). Striping may be applied during nighttime hours (after 6:00 p.m. and before 7:00 a.m.)

Order of paving activities

Grinding removes the old road surface. Expect two days to complete this work – one day for the north lanes and one day for the south lanes. Driveway and pedestrian crossings will be ramped at the end of each day.

Prep work prepares the area to take new paving. Expect one day for this work.

Paving lays down the new road surface. Expect two days to complete this work – one day for the north lanes and one day for the south lanes. Temporary striping will be laid down as each section of paving is completed.

Permanent Striping lays down the new lanes. Temporary striping will be in place until all sections of paving are completed, and then permanent striping will be applied. Striping may include some night work.  All other crosswalk and curb markings will be completed during regular work hours.

For more information

If you have other questions or concerns about the project, contact Joe Annett at 503-823-2934 or joseph.annett@portlandoregon.gov. Noise-related comments will be forwarded to the Noise Office.

To receive regular email updates about this project, please send an email to Joe with “Division” in the subject line. More information about the project is available online at www.portlandoregon.gov/transportation/divisionstreetscape.