Construction Schedule

Below is the estimated construction schedule for two weeks. Please be aware that this schedule is subject to change due to a variety of factors, including conditions underground, weather, traffic impacts, subcontractor schedules and availability of materials.

Week of November 24

  • SE Clinton (SE 33rd Place to 35th Avenue) – Main public sewer pipe, manhole, and lateral construction
  • SE 34th Avenue (at SE Clinton) –  Construction of two green street planters and corner improvement with ADA ramps
  • Miscellaneous finish work throughout the project area
  • Note: Crews will not be working November 27th and 28th 

Week of December 1

  • SE Ivon Street (SE 38th to Cesar Chavez Boulevard) – Main public sewer pipe, manhole, and lateral construction
  • SE 34th Avenue (SE Clinton to Division) – Removal of temporary asphalt and final trench paving
  • SE Clinton (SE 33rd Place to 35th Avenue) – Removal of temporary asphalt and final trench paving
  • SE 34th Avenue (at SE Clinton) –  Construction of two green street planters and corner improvement with ADA ramps
  • Miscellaneous finish work throughout the project area