Below is the estimated construction schedule for the next three weeks. Please be aware that this schedule is subject to change due to a variety of factors, including conditions underground, weather, traffic impacts, subcontractor schedules and availability of materials.

The week of September 26

  • SE 8th Avenue (Taggart to Woodward) – manhole construction
  • SE 11th Avenue (Powell to Brooklyn) – mainline sewer repair
  • Green street planter construction – all locations

Week of October 3

  • SE 8th Avenue (Taggart to Woodward) – manhole construction
  • SE 9th Avenue (Taggart to Woodward) – manhole construction
  • SE 11th Avenue (Powell to Brooklyn) – mainline sewer repair
  • Green street planter construction – all locations

Week of October 10

  • SE 11th Avenue (Powell to Brooklyn) – mainline sewer repair
  • SE 11th Avenue (Franklin to Powell) – tentative street restoration
  • Green street planter construction – all locations

One of the most common questions we receive is “When will construction occur on my street?” Signing up for email updates will allow you to track the movements of work crews and the type of work occurring. Updates generally arrive every one to two weeks and give you a two-week look ahead at planned activity. If you have not already done so, we encourage you to sign up for email updates here.

Thank you in advance for your cooperation during this project. Throughout construction, please contact me if you have questions or concerns at 503-823-5352 or Matthew.Gough@portlandoregon.gov.