Division Streetscape Project Update: April 24, 2014

Division Streetscape Project Update: April 24, 2014

Environmental Services and the Portland Bureau of Transportation are working together to improve the Division Street transportation corridor, repair and replace older sewers, add green infrastructure to manage stormwater and make sewers work more efficiently, and improve watershed health.

WHAT WE’VE HEARD FROM YOU?

We’ve heard questions about when green street stormwater facilities will be planted. That work will take place this coming fall after the final paving is completed.

CONSTRUCTION SCHEDULE

Below is the estimated Division Streetscape construction schedule for the next three weeks. Construction will move from one site to another as crews complete work on each segment. Please be aware that this schedule is subject to change due to conditions underground, weather, traffic impacts, subcontractor schedules and availability of materials.

NOTE: Construction crews are moving “Businesses Open During Construction” signs as they move from work site to work site. Sometimes it may take a day or two to get them completely moved, so please be patient.

Week of April 21:

  • Pour southeast corner at SE Division and 25th Avenue
  • Form and pour corners and ramps at 26th Avenue
  • Prep curb, sidewalk and ramps at SE 28th Avenue (north side)
  • Form and pour at SE 28th Avenue (north side)
  • Form and pour curbs, sidewalks and ramps at 28th Place
  • Form and pour sidewalk and ramps at SE Division Street and 29th Avenue (north side)
  • Finish excavation, install liners, and place rock check dams for stormwater facility at SE Division Street and 29th Avenue (north side)
  • Prep curb, sidewalk and ramps SE Division Street and 30th Avenue (NE corner)
  • Excavate stormwater facilities on SE 30th Avenue at Division Street and the facility on north side of Division at 30th Avenue

Week of April 28:

  • Pour bus stop at 26th Avenue (rider information posted at location)
  • Form and pour curbs, sidewalks and ramps at 28th Place
  • Finish excavation, install liner, and place rock check dams for stormwater facility on SE 28th Place at Division
  • Form and pour, finish excavation and install liners for stormwater facilities on SE 30th Avenue at Division Street and the facility on north side of Division at 30th Avenue
  • Form and pour sidewalk and ramps at SE Division and 30th Avenue
  • Prep curb, sidewalk and ramps at SE Division Street and 28th Place (north side)
  • Excavate stormwater facilities on SE 28th Place then form and pour along with the sidewalk and ramps
  • Prep curb, sidewalk and ramps at northwest corner of SE 30th Avenue and Division Street
  • Trenching for inlet leads/laterals at 18th and 19th avenues, and areas between 13th and 25th avenues

Week of May 5:

  • Install topsoil for stormwater facility on SE 28th Place at Division Street
  • Install topsoil for stormwater facility at SE Division Street and 29th Avenue. (north side
  • Place rock check dams and install topsoil for stormwater facilities on SE 30th Avenue at Division Street and the facility on north side of Division at 30th
  • Finish excavating stormwater facilities on SE 28th Place, then install liners
  • Place rock check dams at stormwater facilities at SE Division Street and 29th Avenue (north side)
  • Prep curb, sidewalk and ramps at northwest corner of SE 30th Avenue and Division Street
  • Form and pour northwest corner of SE 30th Avenue and Division Street
  • Prep curb, sidewalk and ramps on north side of SE Division Street at 31st Avenue
  • Excavate, then form and pour stormwater facilities on SE Division Street at 31st Avenue (north side)
  • Form and pour sidewalk and ramps at SE Division Street and 31st Avenue
  • Prep curb, sidewalk and ramps, then form and pour at northwest corner of SE Division Street at 32nd Avenue (north side)

As always, please follow the direction of flaggers and informational signs to ensure everyone’s safety.

FOR MORE INFORMATION

Go to www.portlandonline.com/transportation/divisionstreetscape to see background information and block-by-block maps of the design. To receive email updates for this project, send an email to joseph.annett@portlandoregon.gov with “Division” in the subject line.

Thank you for your cooperation during this project. Please let us know if you have concerns such as business operations, disability issues, or medical or business deliveries. As always, we’ll strive to provide quick response to your concerns, minimal disruption near your residence or business, and open and clear communication with you throughout the project.

Joe Annett

Community Outreach

City of Portland Environmental Services

1120 SW 5th Avenue, Room 1000, Portland, OR 97204-3713

Phone: 503-823-2934

Email: joseph.annett@portlandoregon.gov

Tabor to the River Program

This project is part of the Tabor to the River Program, which combines innovative stormwater management techniques with sewer repairs and improvements to stop basement flooding, manage stormwater more naturally, and to restore watershed health. The program area extends from Mt. Tabor to the Willamette River between SE Hawthorne and SE Powell boulevards.