Division Streetscape Project Update: May 8, 2014

Division Streetscape Project Update: May 8, 2014

Environmental Services and the Portland Bureau of Transportation are working together to improve the Division Street transportation corridor, repair and replace older sewers, add green infrastructure to manage stormwater and make sewers work more efficiently, and improve watershed health.

WHAT WE’VE HEARD FROM YOU

We’ve heard continued concerns with the condition of the road surface. Crews will continue to maintain temporary paving as weather permits. We are quickly approaching the repaving portion of the project. This work could be begin as soon as mid-June. The contractor will repave in sections of about seven blocks at a time. Work crews will grind down the street and pave one side at a time, then move to the other side of the street. Work will begin at SE Division and 11th Avenue and progress east along Division. There will be traffic delays and lane restrictions during paving.

CONSTRUCTION SCHEDULE

Here is the estimated Division Streetscape construction schedule for the next three weeks. Construction will move from one site to another as crews complete work on each segment. Please be aware that this schedule is subject to change due to conditions underground, weather, traffic impacts, subcontractor schedules and availability of materials.

NOTE: Construction crews are moving “Businesses Open During Construction” signs as they move from work site to work site. Sometimes it may take a day or two to get them completely moved, so please be patient.

Week of May 5:

  • Form and pour ramp at north side of SE 28th Avenue and Division.
  • Finish excavating stormwater facilities on SE 28th Place at Division.
  • Form and pour sidewalk/ramp at SE 29th Avenue and Division, and finish excavation.
  • Form and pour sidewalk at northeast corner of SE Division and 30th Avenue.
  • Finish excavating stormwater facilities on northeast corner of SE Division and 30th Avenue.
  • Prep curb, sidewalk and ramps at northeast corner of SE Division and 28th Place.
  • Form and pour stormwater facility, sidewalk and ramp on north side of SE Division at 28th Place.
  • Finish excavating stormwater facility on north side of SE Division at 28th Place.
  • Form and pour northwest corner of SE Division and 30th Avenue.
  • Prep curb, sidewalk and ramps on north side of SE Division at 31st Avenue.
  • Excavate stormwater facilities on north side of SE Division at 31st Avenue, then form and pour.
  • Form and pour sidewalk and ramps on north side of SE Division at 31st Avenue.
  • Prep curb, sidewalk and ramps at northwest corner of SE Division and 32nd Avenue, then form and pour.
  • Prep curb, sidewalk and ramps on north side of SE Division at 33rd Avenue, then form and pour.
  • Prep curb, sidewalk and ramps at northwest corner of SE Division and 34th Avenue.
  • Prep concrete corner ramp adjustments.
  • Form and pour concrete corner ramp adjustments and art foundations.
  • Continue trench and asphalt maintenance.

Week of May 12:

  • Install liners, rock/check dams and topsoil in stormwater facilities on SE 28th Place at Division.
  • Install liners, rock/check dams and topsoil in stormwater facilities on the north side of SE Division at 29th Avenue.
  • Install liners, rock/check dams and topsoil in stormwater facilities on northeast corner of SE Division and 30th Avenue.
  • Finish excavating stormwater facility on north side of SE Division at 28th Place, and install liner, rock/check dam and topsoil.
  • Finish excavation of stormwater facilities on the north side of SE Division at 31st Avenue, then install liner, rock/ check dams and topsoil.
  • Form and pour curb, sidewalk and ramps at northwest corner of SE Division and 34th Avenue.
  • Prep curb, sidewalk and ramps at northeast corner of SE Division and 32nd Avenue, then form and pour.
  • Prep curb, sidewalk and ramps at northeast corner of SE Division and 34th Avenue, then form and pour.
  • Excavate stormwater facility on north side of SE Division east of 34th Avenue.
  • Excavate bus stop on northeast corner of SE Division and 34th Avenue, then form and pour.
  • Excavate bus stop on northeast corner of SE Division and 26th Avenue, then form and pour.
  • Continue trench and asphalt maintenance.

As always, please follow the direction of flaggers and informational signs to ensure everyone’s safety.

FOR MORE INFORMATION

Go to www.portlandonline.com/transportation/divisionstreetscape to see background information and block-by-block maps of the design. To receive email updates for this project, send an email to joseph.annett@portlandoregon.gov with “Division” in the subject line.

Thank you for your cooperation during this project. Please let us know if you have concerns such as business operations, disability issues, or medical or business deliveries. As always, we’ll strive to provide quick response to your concerns, minimal disruption near your residence or business, and open and clear communication with you throughout the project.

Joe Annett

Community Outreach

City of Portland Environmental Services

1120 SW 5th Avenue, Room 1000, Portland, OR 97204-3713

Phone: 503-823-2934

Email: joseph.annett@portlandoregon.gov

Tabor to the River Program

This project is part of the Tabor to the River Program, which combines innovative stormwater management techniques with sewer repairs and improvements to stop basement flooding, manage stormwater more naturally, and to restore watershed health. The program area extends from Mt. Tabor to the Willamette River between SE Hawthorne and SE Powell boulevards.