Division Streetscape Project Update: May 30, 2014

Division Streetscape Project Update: May 30, 2014

Environmental Services and the Portland Bureau of Transportation are working together to improve the Division Street transportation corridor, repair and replace older sewers, add green infrastructure to manage stormwater and make sewers work more efficiently, and improve watershed health.

DEVELOPMENTS OF NOTE

The Division Streetscape Project has progressed to where paving is expected to begin on June 14 between SE 11th Avenue and Cesar Chavez Boulevard (39th Avenue), weather permitting. After paving is completed, permanent striping will be applied. The Portland Noise Office granted Environmental Services a noise variance that will enable the work to occur weekdays and weekends, with some work occurring at night. The first section of paving work will begin on SE Division between 11th and 12th avenues, and will take place during the weekend, from 7:00 a.m. to 6:00 p.m. on both Saturday and Sunday, June 14-15. For the full paving plan, visit the web page at www.portlandoregon.gov/bes/article/491779.

 

CONSTRUCTION SCHEDULE

Here is the estimated Division Streetscape construction schedule for the next three weeks. Construction will move from one site to another as crews complete work on each segment. Please be aware that this schedule is subject to change due to conditions underground, weather, traffic impacts, subcontractor schedules and availability of materials.

NOTE: Construction of the Clinton Green Street and Sewer Project will begin in early July. For information on this project please visit the web page at www.portlandoregon.gov/bes/Clinton.

This week:

  • West side of 28th Place at Division – Install topsoil in stormwater facility
  • North side of Division at 29th Avenue – Install topsoil in stormwater facility
  • East side of 30th Avenue north of Division – Install topsoil in stormwater facility
  • North side of Division east of 28th Place – Install topsoil in stormwater facility
  • North side of Division at 31st Avenue – Finish excavating stormwater facility, install liner, place rock/check dams
  • North side of Division east of 35th Avenue – Finish excavating stormwater facility
  • North side of Division at 35th Avenue – Prep curb, sidewalk and ramps, form and pour stormwater facility
  • NW corner of Division and 35th Place – Prep curb sidewalk and ramps, then forma and pour
  • NE corner of Division and 35th Place – Prep curb sidewalk, and ramps
  • North side of Division west of 36th Avenue – Prep for stormwater facility, form and pour
  • NW corner of Division and 37th Avenue – Prep curb, sidewalk, and ramps, then form and pour

Week of June 2:

  • East side of 30th Avenue north of Division – Install topsoil in stormwater facility
  • North side of Division at 31st Avenue – Install topsoil in stormwater facility
  • North side of Division east of 35th Avenue – Install liner in stormwater facility, and place rock/check dams
  • North side of Division at 35th Avenue – Finish excavation of stormwater facility, install liner, and place rock/check dams
  • NE corner of Division and 35th Place – Prep curb sidewalk and ramps, then forma and pour, finish excavation of stormwater facility
  • NE corner of Division and 35th Place – Finish excavation of stormwater facility, install liner
  • North side of Division west of 36th Avenue – Finish excavation of stormwater facility, install liner, place rock/check dams
  • NW corner of Division and 37th Avenue – Form and pour stormwater facility, finish excavation, and install liner
  • NE corner of Division and 37th Avenue – Prep curbs, sidewalk and ramps, form and pour
  • NW corner of Division and 38th Avenue – Prep curbs, sidewalk and ramps, form and pour

Week of June 9:

  • North side of Division east of 35th Avenue – Install topsoil in stormwater facility
  • North side of Division at 35th Avenue – Install topsoil stormwater facility
  • NE corner of Division and 35th Place – Place rock/check dams in stormwater facility, and install topsoil
  • North side of Division west of 36th Avenue – Install topsoil in stormwater facility
  • NW corner of Division and 37th Avenue – Place rock/check dams in stormwater facility, and install topsoil
  • NE corner of Division and 37th Avenue – Finish excavation of stormwater facility, install liner, place rock/check dams, and install topsoil
  • NE corner of Division and 38th Avenue – Prep curbs, sidewalk and ramps, then Form and pour
  • SE/SW corners of Division and 38th Avenue – Prep curbs, sidewalk and ramps, form and pour

Weekend of June 14-15:

  • SE Division between SE 11th and SE 12th avenues – Paving will occur both Saturday and Sunday from 7:00 a.m. to 6:00 p.m. For details, visit the web page at www.portlandoregon.gov/bes/article/491779.

As always, please follow the direction of flaggers and informational signs to ensure everyone’s safety.

Asphalt maintenance continues for all Division Streetscape work to patch areas until final paving occurs.

FOR MORE INFORMATION

Go to www.portlandonline.com/transportation/divisionstreetscape to see background information and block-by-block maps of the design. To receive email updates for this project, send an email to joseph.annett@portlandoregon.gov with “Division” in the subject line.

Thank you for your cooperation during this project. Please let us know if you have concerns such as business operations, disability issues, or medical or business deliveries. As always, we’ll strive to provide quick response to your concerns, minimal disruption near your residence or business, and open and clear communication with you throughout the project.

Joe Annett

Community Outreach

City of Portland Environmental Services

1120 SW 5th Avenue, Room 1000, Portland, OR 97204-3713

Phone: 503-823-2934

Email: joseph.annett@portlandoregon.gov

Tabor to the River Program

This project is part of the Tabor to the River Program, which combines innovative stormwater management techniques with sewer repairs and improvements to stop basement flooding, manage stormwater more naturally, and to restore watershed health. The program area extends from Mt. Tabor to the Willamette River between SE Hawthorne and SE Powell boulevards.