PROJECT OVERVIEW

Thanks to funding from the Parks Replacement Bond, St. Johns Community Center will receive a roof replacement and a replacement HVAC system to improve heating and cooling. 

The Community Center will remain open during construction, and we anticipate being able offer all regular activities and services.  Visitors may notice construction fencing, noise, and other construction impacts. 

Construction Manager
Marlo Medellin, marlo.medellin@portlandoregon.gov, (503) 823-5581

Public Involvement Coordinator
Maija Spencer, maija.spencer@portlandoregon.gov, (503) 823-5593


PROJECT UPDATE

This project was originally planned for construction in Summer 2016. It was put out for bid in Spring 2016 but was cancelled due to insufficient bids. The project will go out for bid in January 2017, with planned construction in Summer 2017. 


 PROJECT SCHEDULE

Fall 2015 - Winter 2015/16
Design Development

Winter 2016/17 - Spring 2017
Permitting and Bidding

June 2017 - September 2017
Constructiont description