NE 112th Avenue & Marx Street LID

LID formed by City Council on March 7, 2012

Design for Phase I work completed May 9, 2014.

Advertised for bids for Phase I construction work on May 19, 2014.

Opened bids for Phase I construction work on June 12, 2014.

Executed contract with Kodiak Pacific Construction, Inc. on July 31, 2014.

Phase I Project Plans (42 Mb)

Issued Notice to Proceed to Kodiak Pacific Construction, Inc. on August 25, 2014.

Schedule for first phase of construction (NE Marx Street) provided by Kodiak Pacific Construction, Inc. on September 10, 2014:

   Week of September 15, 2014 through September 19, 2014

   Complete remaining utility relocation

   Finalize plan for storm sewer revision at intersection of NE 112th Avenue & Marx Street

   Week of September 22, 2014 through September 26, 2014

   Begin construction of storm sewer

   Week of September 29, 2014 through October 3, 2014

   Continue construction of storm sewer

Construction for Phase II construction work (NE 112th Avenue) scheduled for spring 2015.

Streets include:

  • NE Marx Street from NE 109th Avenue to NE 112th Avenue (Phase I work); north side of street only except for 11040 NE Marx St.
  • NE 112th Avenue from NE Marx Street to the north property line of 5415 NE 112th Avenue (Phase II work)

Property owners are funding most costs of the project with a fixed contribution of $100,000 from the Bureau of Environmental Services.

If you have any questions about this project, please contact Local Improvement District Administrator and Project Manager at 503-823-5648 or via e-mail at andrew.aebi@portlandoregon.gov