UPDATES

August 13, '14

Anticipated construction activity: 

Week of August 11:  Completion of curb and sidewalk at SE 52nd Ave/Division

Week of August 18:  Continued work at NE 53rd/ Burnside,; signal work at SE 52nd Ave/Division

 

July 15, 2014 

Anticipated construction activity:

July 15- 31:  SE Stark/ 53rd curb ramps, SE Woodward/ 52nd curb extensions, E Burnside/ 53rd signal and diversion work, SE 52nd/ Powell to Division restriping

August: SE Stark/ 53rd median islands, E Burnside/ 53rd signal and diversion work, SE Division/ 52nd Ave: signal and diversion work, NE Thompson to Division: signing and striping.

September:  Complete signal work at E Burnside/ 53rd and SE Division/ 52nd Ave

 

 

June 10, 2014

Construction activity will take place over the next 2 weeks at SE Lincoln/52nd Ave, SE Woodward/ 52nd Ave, and SE Stark/ 53rd Ave for crossing improvements.  During the week of June 23, restriping of SE 52nd Ave between SE Powell Blvd and Woodstock Blvd is anticipated.

 

 

April 29, 2014

FINALLY!

We are ready to go to construction!  Construction is aniticpated to start the week of May 5.

The general sequence of construction events is as follows:

The contractor will begin with work on the crossing improvements, starting with SE Woodward and proceed north (Division, Lincoln, Stark and Burnside).  This work is anticipared to be completed mid-late June.  Striping and all pavement markings (sharrows) will follow, taking about a week to complete (weather permitting).  The speed bumps will also be constructed in this time frame.  The final piece work is the signal work at SE Division/52nd Ave and E Burnside/ 53rd Ave, which is anticipated to be completed by the end of July.

Monitoring and evaluation of the two diversion locations, SE Division/52nd Ave and E Burnside/ 53rd Ave, per the City Council recommendation, will begin shortly after the project is completed, lasting for 6 months.

 

 

March 20, 2014

We are still working with the contractor to complete the construction contract documents and hope to be able to begin work in early April.  Your patience is appreciated.

 

January, 2014

Construction is anticipated to begin in late March of 2014.

 

 

November, 2013:  Rebid

The project will be going to bid on November 25.  If all goes well with the bids, the start of construction is anticipated for March of 2014.

 

 

July, 2013

The project was put out to bid in June with the bid opening on July 9.  Unfortunately, the bids received were all substantially above the project's construction budget and original cost estimate.  This indicates that the construction market is currently saturated with work.   As a result, we will be re-bidding the project in November.  The new anticipated construction start date is February, 2014.  We appreciate your patience.