SW 11th Avenue Project

Design completed on June 27, 2012

Advertising for bids on July 9, 2012

Opened bids on July 26, 2012

Awarded contract on September 18, 2012

The first phase of construction consisting primarily of concrete work (curbs, sidewalks and driveways), began on November 5, 2012 and was completed on January 22, 2013.

The second phase of construction consisting of street reconstruction and additional concrete work (additional curbs, sidewalks and driveways), began on June 24, 2013 with SW 11th Avenue reopened to traffic on August 8, 2013 and substantial completion by the contractor on August 16, 2013.  Additional sidewalk work was included in the second phase of construction to complete the pedestrian connection on both sides of SW 11th Avenue from SW Gibbs Street to SW Gaines Street.

Tree planting is tentatively scheduled for Fall 2014; no more schedule updates are planned.

Project included:

  • SW 11th Avenue from Curry Street to Whitaker Street 
  • SW 11th Avenue from Whitaker Street to Gibbs Street 

Design and construction of this project was fundied by Marquam Hill parking meter revenue and sidewalk infill funding.

If you have any questions about the project, please contact project manager Andrew Aebi at 503-823-5648 or e-mail at andrew.aebi@portlandoregon.gov.

 

Click here to see project plans.