The Transportation Bureau manages a wide array of projects that improve Portland's streets. Planning for these projects may be done years in advance for major projects or spur-of-the-moment for emergencies and minor repairs. Regardless, PBOT is constantly working to keep our streets in the best condition possible with the local funds we have and the state and national funds we seek.
Below is a table of significant projects that are currently funded and scheduled. For a list of unfunded projects for Portland, visit the Transportation System Plan. We are not including minor repairs because there are too many done every day to efficiently record in a table.
Updated: October 24, 2012 (Schedule subject to change due to weather, budget and other unforeseen events)
| STREET | WHAT'S HAPPENING | LOCATION | WHEN | NOTES |
| NORTH PORTLAND | ||||
| Burgard Road, N | Paving | Over abandoned railroad | FY 2012-13 | |
| Portland Road, N | Paving | 64m north of structure to N Marine Dr | COMPLETED | |
| Vancouver Way, N | Paving | NE 3rd Ave to N Marine Dr | June 17-27, 2013 | |
| NORTHEAST PORTLAND | ||||
| 21st Avenue, NE | Bridge rehabilitation | NE 21st Ave Bridge over Columbia Slough | Summer 2012 | Project extended into Fall 2012 to modernize bridge supports and foundation |
| 42nd Avenue, NE | Bridge resurfacing | NE 42nd Ave bridge over Portland Highway | COMPLETED | |
| 97th Avenue, NE | Property owner funded LID street construction | NE Everett Pl: NE 97th Ave to NE 99th Ave | FY 2012-13 | Local improvement district |
| 122nd Avenue, NE | Paving | NE Holladay St to NE Halsey St | COMPLETED | |
| 136th Avenue, NE | Property owner funded LID street construction | 364 ft north of NE Prescott Ct to NE Whitaker Way | FY 2012-13 | Local improvement district |
| Alberta Street, NE | Property owner funded LID street construction | NE 76th Ave to NE 79th Ave | FY 2012-13 | Local improvement district |
| Columbia Boulevard, NE | Bridge resurfacing | NE Columbia Blvd over NE 33rd Dr | COMPLETED | |
| Cully Boulevard, NE | Paving | NE Failing St to NE 60th Ave | June 3-7, 2013 | |
| Halsey Street, NE | Paving | NE 84th Ave to NE 92nd Ave | June 10-14, 2013 | |
| Marine Drive, NE | Paving | Weather Station to 1,500 ft west of I-205 | COMPLETED | |
| Multnomah Street, NE | Paving | NE 1st Ave to NE Martin Luther King Jr. Blvd | October 25 - November 6, 2012 | Street repaving plus new lane striping, signal timing adjustments, traffic delineators and potted planters; schedule delayed 3 working days due to weather |
| Sandy Boulevard, NE | Capital improvement paving | NE 47th Ave to NE 82nd Ave | COMPLETED | Street repaving plus curb ramps, traffic signals, stormwater planters and new sewers |
| SOUTHEAST PORTLAND | ||||
| 82nd Ave, SE | Property owner funded LID street construction | SE Bybee Blvd to 168 ft south of Cooper Street | FY 2012-13 | Local improvement district |
| 118th Ave, SE | Property owner funded LID street construction | SE Pardee St to SE Liebe St | FY 2012-13 | Local improvement district |
| 122nd Ave, SE | Bridge rehabilitation | SE 122nd Ave Bridge over Johnson Creek | COMPLETED | Bridge deck rehabilitation and repaving |
| 162nd Ave, SE | Sidewalk infill | SE Powell Blvd to SE Salmon St | Oct. 2012 - May 2013 | |
| Bybee Blvd, SE | Property owner funded LID street constuction | SE 82nd Ave to 37 ft east of SE 81st Pl | FY 2012-13 | Local improvement district |
| Division Street, SE | Capital improvement street reconstruction | SE 11th Ave to SE Cesar Chavez Blvd | Jan. 2013 - Fall 2013 | Streetscape project includes street reconstruction and paving plus street trees, bioswales, curb extensions, crosswalks, street lights, traffic signals, sewers and public art |
| Foster Road-Woodstock Boulevard, SE | Capital improvement streetscape | Various streets | Oct. 2012 - May 2013 | Streetscape project includes street reconstruction and paving plus sidewalk reconstruction, street lights, street trees, intersection and crosswalk improvements, new traffic signal and on-street parking |
| Stark Street, SE | Sidewalk infill | SE 126th Ave to SE 162nd Ave | Oct. 2012 - May 2013 | |
| Washington Street, SE | Paving | SE 82nd Ave to SE 90th Ave | COMPLETED | |
| NORTHWEST PORTLAND | ||||
| 16th Avenue, NW | Paving | NW Lovejoy St to NW Thurman St | COMPLETED | |
| Burnside Road, W | Paving | NW Skyline Blvd to the tunnel | COMPLETED | |
| Thurman Street, NW | Paving | NW Gordon St to NW 31st Ave | COMPLETED | |
| SOUTHWEST PORTLAND | ||||
| 11th Avenue, SW | Capital improvement paving | SW Curry St to SW Gibbs St | FY 2012-13 | |
| 11th Avenue, SW | Sidewalks | SW Gaines St to SW Gibbs St | FY 2012-13 | New sidewalks on east side of street |
| Barbur Boulevard, SW | Paving | SW Sheridan St to SW Viewpoint Ter | Oct. 8-24, 2012 | Schedule and scope changed due to Portland-Milwaukie Light Rail construction activities; schedule extended due to weather |
| Capitol Highway, SW | Bridge rehabilitation | COMPLETED | Bridge concrete substructure modernization | |
| Naito Parkway, SW | Capital improvement street reconstruction | SW Jefferson St to I-405 | FY 2013-14 | |
| Pine Street, SW | Paving | SW 4th Ave to SW Naito Pkwy | May 27-31, 2013 | |
| Stark Street, SW | Paving | SW 10th Ave to SW Broadway | May 20-24, 2013 |
|