Construction Schedule

Sept 26, '16 Update:  next two weeks

Crossing improvement work:

  • SE Stark/ 30th Ave:  work continues
  • NE Glisan/ 30th Ave:  work continues
  • NE Broadway/ 26th Ave:  work continues
  • SE Belmont/ 29th Ave:  work continues

Speed bumps:

  • NE 26th Ave: Halsey to Regents
  • NE Regents to Lombard

Striping:

  • SE 28th Place
  • NE 30th Ave:  Couch to Hoyt

 

Sept 19, '16 Update:  next two weeks

Crossing improvement work:

  • SE Stark/ 30th Ave:  work continues
  • NE Glisan/ 30th Ave:  work continues
  • NE Broadway/ 26th Ave:  work begins
  • SE Belmont/ 29th Ave:  work begins
  • SE Hawthorne/ 29th Ave:  work begins (revised)

Speed bumps:

  • NE 26th Ave: Halsey to Regents
  • NE Regents
  • NE 32nd Ave: Morris to Holman

Striping:

  • SE 28th Place
  • NE 30th Ave:  Couch to Hoyt

 

 

Sept 12, '16 Update:  next two weeks

    • N Burnside/ 30th Ave
    • SE Stark/ 30th Ave
    • NE Glisan/ 30th Ave

    Crossing improvement work will continue at these three intersections

Speed Bumps:

  • NE 26th Ave:  Tillamook to Regents

Striping & Signing

  • NE 26th Ave:  Tillamook to Regents
  • NE 32nd and 27th Ave:  Mason to Lombard
  • SE Crystal Springs Blvd:  45th to 32nd Ave

 

Sept 1, '16 Update:  next two weeks

  • N Burnside/ 30th Ave
  • SE Stark/ 30th Ave
  • NE Glisan/ 30th Ave

Crossing improvement work will continue at these three intersections

  • SE Crystal Springs/ 45th to 32nd Ave

Installation of speed bumps and signage

  • SE 28th Ave/ Clinton to Harrison & SE 32nd Ave/ Crystal Springs to Woodstock

Installation of signage

  • NE 30th Ave/ Couch to Weidler

Installation of 'sharrow' pavement markings, speed bumps and signage

August, 2016

Construction activity is anticipated to begin the week of August 8th.  Overall, its is anticipated that work will begin with signing, striping and installation of speed bumps from the south end of the project area to the north.

General Construction Schedule- subject to change due to weather and other delays

Signing/ Striping/ Speed Bumps:

  • SE Crystal Springs Blvd:  8/10 to 8/24
  • SE 32nd Ave/ Eastmoreland:  8/25 to 9/1
  • SE Woodstock Blvd:  9/2 to 9/9
  • SE 28th-  Holgate to Harrison:  9/2 to 9/21
  • SE 29th- Harrison to Washington:  10/4 to 10/21
  • SE/NE 28th & 30th-  Washington to Wasco:" 10/4 to 10/21
  • NE 26th Ave- Multnomah to Regents:  9/20 to 10/10
  • NE Regents/ 32nd Ave to Lombard:  11/3 to 12/7
  • NE Ainsworth/ 32nd Ave: 12/6 to 12/26
    • NE Dekum/ 27th Ave:  12/6 to 1/2/17

Signals

  • E Burnside/ 30th Ave:  8/8 to 11/17
  • SE Stark/ 30th Ave" 8/18 to 11/18
  • SE Hawthorne/ 29th Ave:  8/18 to 12/1
  • SE Powell/ 28th Ave:  9/8 to 12/5
  • NE Broadway/ 26th Ave:  9/29 to 12/7

Concrete Work

  • NE Glisan/ 30th Ave median:  8/8 to 9/21
  • SE Belmont/ 29th median: 9/15 to 10/21
  • SE Powell Blvd/ 28th Place island removal:  10/14 to 10/27
  • NE Wasco/ 28th Ave curb extensions:  10/20 to 11/2
  • NE Fremont/ 26th Ave:  10/20 to 11/18
  • NE Buxton/ 28th Ave island reconstruction:  10/20 to 12/12
  • NE Alberta/ 32nd Ave curb extensions:  10/28 to 11/29
  • NE Killingsworth/ 32nd Ave curb extensions:  10/28 to 11/29