Section of SE Alder Street closes
Section of SE Alder Street closes
June 13, 2011
Street restoration work has closed SE Alder Street to through traffic between Martin Luther King Jr. Boulevard and SE 3rd Avenue. The city's contractor maintains local access to properties in the construction zone. The closure will remain in effect all days and all hours through this August.
The street restoration will also periodically close some traffic lanes on SE 3rd Avenue between SE Morrison and SE Washington streets.
The street restoration follows work to connect the existing outfalls to the new East Side Big Pipe. The East Side project is part of Portland's 20-year program to control combined sewer overflows (CSOs).
For more information contact Linc Mann, 503-823-5328.