North Winchell Street LID
Advertised for bids on March 24, 2008.
Contract awarded to Parker Northwest Paving on May 21, 2008.
City Engineer issued Notice to Proceed to contractor on June 20, 2008.
Paving completed on August 25, 2008
Tree planting completed on November 3, 2008
Swale vegetation planting completed on November 12, 2008
Final assessment completed on 12/17/08
Streets included:
- North Winchell Street from Montana Avenue to existing curbs west of Minnesota Avenue
Property owners funded this local improvement district.
Final Construction Plans:
Link to plans (Adobe PDF 2.13MB)