Construction Schedule
May 24, '17 Update
If the dry weather holds . . . the project should be substantially complete by the June 9th!
In the next two and a half weeks construction activity will focusing on the following final elements:
- Speed bumps: Hawthorne to Burnside/ 28th Ave from Stark to Glisan
- Intersection improvements: striping crosswalks at SE Woodstock, SE Powell, SE Belmont, and SE Stark St.
- Bicycle lanes: SE 30th Ave, Washington to Stark, NE 28th Ave, Hoyt to Wasco; and SE Woodstock, 28th to 32nd Ave
- Loop detection: SE Powell Blvd and SE Stark St
March 29, '17 Update: Next two weeks:
- SE Powell/ 28th Ave crossing- pour and finish island
- SE Holgate/ 28th Ave- form and pour median island
- SE Woodstock/ 28th Ave- our and finish island
Striping: work still contingent on dry weather. Completion of all crossing improvements still need crosswalk striping before they can be opened or activated.
Project completion is anticipated in mid-May.
February 23, '17 Update: Next Two Weeks
Concrete Work:
- NE Wasco: finish curb extension work
- SW Belmont/ 29th Ave: build SE corner curb ramp
- SE Holgate diverter: build island
Speed Bumps (as weather allows):
- SE Hawthorne to Burnside (as weather allows)
SE Powell Crossing
- Work begins this week and will take approximately one month to complete
Striping
- There is still allot of striping work to be done that is still waiting for suitable weather.
February 8, '17 Update: next two weeks
Gah!- this weather! Please note that our ability to activate the signalized crossing improvements at SE Hawthorne, SE Stark, E Burnside and NE Broadway have been significantly delayed by the weather. We need to complete the associated crosswalk striping at these locations before we can turn on the signals. We need 3 consecutive days of dry weather before we can paint striping to the roadway. Your patience is appreciated.
Concrete construction work:
- SE 28th Ave/ Woodstock island
- SE Belmont/ 29th Ave islands
- SE Belmont SW corner curb ramp
- SE Holgate/ 28th Ave diverter island
- NE Wasco/ 28th Ave curb extension
Speed Bumps:
- SE Hawthorne to SE Burnside (weather dependent)
Signage:
- NE 32nd Ave, Knott to Lombard
January 31, '17 Update: next two weeks
Crossing improvement work:
- NE Wasco/ 28th Ave: curb extensions
- NE Glisan/ 30th Ave: median islands
- SE Belmont/ 29th: median islands
- SE Woodstock/ 28th Ave: median island
- SE Holgate/ 28th Ave: median island
- SE Powell/ 28th Ave: median and signal (night work)
Speed Bumps
- SE Hawthorne to Burnside: weather permitting
While the signal work at SE Hawthorne, Stark, Burnside and Broadway is nearing completion, the crossings will not be operation potentially for the next several months due to weather that prevents us from doing the final striping.
January 2, '17 Update: next two weeks
Crossing improvement work:
- NE Killingsworth/ 32nd Ave: SW corner
- NE Wasco/ 28th Ave: curb extensions
- NE Glisan/ 30th Ave: median island
- SE Belmont/ 29th: median island
- SE Woodstock/ 28th Ave: median island
- SE Powell/ 28th Ave: median and signal (night work)
While the signal work at SE Hawthorne, Stark, Burnside and Broadway is nearing completion, the crossings will not be operation potentially for the next several months due to weather that prevents us from doing the final striping.
Dec 6, '16 Update: next two weeks
Crossing improvement work:
- NE Fremont/ 26th Ave: work continues
- SE 28th Ave/ Buxton & Randall
- SE Powell/ 28th Ave
While the signal work at SE Hawthorne, Stark, Burnside and Broadway is nearing completion, the crossings will not be operation potentially for the next several months due to weather that prevents us from doing the final striping.
SE Holgate diverter & NE Glisan median island
Due to weather that limits our ability to do the associated striping work, construction at these locations will likely be delayed for several months.
Nov 28, '16 Update: next two weeks
Crossing improvement work:
- NE Broadway/ 26th Ave: signal foundation work work continues
- SE Belmont/ 29th Ave: work resumes after holidays
- SE Hawthorne/ 29th Ave: signal work completion
- NE Fremont/ 26th Ave: work continues
- NE Alberta/ 32nd Ave: curb extension work continues
- NE Dekum/ 32nd Ave: curb ramp work continues
Speed bumps: Weather is now makes it likely that continued work will wait until after new year
- NE 29th Ave: Hawthorne to Burnside
- NE 28th Ave: Stark to Sandy
Striping: Weather is now makes it likely that continued work will wait until after new year
Oct 24, '16 Update: next two weeks
Crossing improvement work:
- NE Broadway/ 26th Ave: signal foundation work work continues
- SE Belmont/ 29th Ave: ADA ramp reconstruction work continues
- SE Hawthorne/ 29th Ave: signal foundation work begins
- NE Fremont/ 26th Ave: curb extension work begins
- NE Alberta/ 32nd Ave: curb extension work begins
- NE Killingsworth/ 32nd Ave: curb extension work begins
Speed bumps: Weather is now becoming more of a scheduling issue with speed bump work
- NE 26th Ave: Halsey to Regents
- NE Regents to Lombard
Striping: Weather is now becoming more of a scheduling issue with striping work
- SE 28th Place
- NE 30th Ave: Couch to Hoyt
Oct 3, '16 Update: next two weeks
Crossing improvement work:
- SE Stark/ 30th Ave: signal pole foundation and curb ramp work continues,
- NE Glisan/ 30th Ave: work continues: form and pore median island
- NE Broadway/ 26th Ave: signal foundation work work continues
- SE Belmont/ 29th Ave: ADA ramp reconstruction work continues
- SE Hawthorne/ 29th Ave: signal foundation work begins
- NE Alberta: curb extension work begins
Speed bumps: Weather is now becoming more of a scheduling issue with speed bump work
- NE 26th Ave: Halsey to Regents
- NE Regents to Lombard
Striping: Weather is now becoming more of a scheduling issue with striping work
- SE 28th Place
- NE 30th Ave: Couch to Hoyt
Sept 26, '16 Update: next two weeks
Crossing improvement work:
- SE Stark/ 30th Ave: work continues
- NE Glisan/ 30th Ave: work continues
- NE Broadway/ 26th Ave: work continues
- SE Belmont/ 29th Ave: work continues
Speed bumps:
- NE 26th Ave: Halsey to Regents
- NE Regents to Lombard
Striping:
- SE 28th Place
- NE 30th Ave: Couch to Hoyt
Sept 19, '16 Update: next two weeks
Crossing improvement work:
- SE Stark/ 30th Ave: work continues
- NE Glisan/ 30th Ave: work continues
- NE Broadway/ 26th Ave: work begins
- SE Belmont/ 29th Ave: work begins
- SE Hawthorne/ 29th Ave: work begins (revised)
Speed bumps:
- NE 26th Ave: Halsey to Regents
- NE Regents
- NE 32nd Ave: Morris to Holman
Striping:
- SE 28th Place
- NE 30th Ave: Couch to Hoyt
Sept 12, '16 Update: next two weeks
-
- N Burnside/ 30th Ave
- SE Stark/ 30th Ave
- NE Glisan/ 30th Ave
Crossing improvement work will continue at these three intersections
Speed Bumps:
- NE 26th Ave: Tillamook to Regents
Striping & Signing
- NE 26th Ave: Tillamook to Regents
- NE 32nd and 27th Ave: Mason to Lombard
- SE Crystal Springs Blvd: 45th to 32nd Ave
Sept 1, '16 Update: next two weeks
- N Burnside/ 30th Ave
- SE Stark/ 30th Ave
- NE Glisan/ 30th Ave
Crossing improvement work will continue at these three intersections
- SE Crystal Springs/ 45th to 32nd Ave
Installation of speed bumps and signage
- SE 28th Ave/ Clinton to Harrison & SE 32nd Ave/ Crystal Springs to Woodstock
Installation of signage
- NE 30th Ave/ Couch to Weidler
Installation of 'sharrow' pavement markings, speed bumps and signage
August, 2016
Construction activity is anticipated to begin the week of August 8th. Overall, its is anticipated that work will begin with signing, striping and installation of speed bumps from the south end of the project area to the north.
General Construction Schedule- subject to change due to weather and other delays
Signing/ Striping/ Speed Bumps:
- SE Crystal Springs Blvd: 8/10 to 8/24
- SE 32nd Ave/ Eastmoreland: 8/25 to 9/1
- SE Woodstock Blvd: 9/2 to 9/9
- SE 28th- Holgate to Harrison: 9/2 to 9/21
- SE 29th- Harrison to Washington: 10/4 to 10/21
- SE/NE 28th & 30th- Washington to Wasco:" 10/4 to 10/21
- NE 26th Ave- Multnomah to Regents: 9/20 to 10/10
- NE Regents/ 32nd Ave to Lombard: 11/3 to 12/7
- NE Ainsworth/ 32nd Ave: 12/6 to 12/26
- NE Dekum/ 27th Ave: 12/6 to 1/2/17
Signals
- E Burnside/ 30th Ave: 8/8 to 11/17
- SE Stark/ 30th Ave" 8/18 to 11/18
- SE Hawthorne/ 29th Ave: 8/18 to 12/1
- SE Powell/ 28th Ave: 9/8 to 12/5
- NE Broadway/ 26th Ave: 9/29 to 12/7
Concrete Work
- NE Glisan/ 30th Ave median: 8/8 to 9/21
- SE Belmont/ 29th median: 9/15 to 10/21
- SE Powell Blvd/ 28th Place island removal: 10/14 to 10/27
- NE Wasco/ 28th Ave curb extensions: 10/20 to 11/2
- NE Fremont/ 26th Ave: 10/20 to 11/18
- NE Buxton/ 28th Ave island reconstruction: 10/20 to 12/12
- NE Alberta/ 32nd Ave curb extensions: 10/28 to 11/29
- NE Killingsworth/ 32nd Ave curb extensions: 10/28 to 11/29