Final Building Inspection vs. Final Permit Inspection

There has been some confusion over the two final inspections "299 Final – Structural" and "999 Final Permit." To clarify, "299 Final – Structural" can only be used on RS, MP and MI permits. The purpose of this inspection is to get a final only for the building piece of the job. 999 Final is used to final the whole project. For finals on Commercial Building Permits, customers should request inspection 999.