How do I submit Deferred Submittals & Revisions?

When submitting Deferred Submittals & Revisions you must fill out an FPP Deferred Submittal or Revision application.

Deferred Submittal:

  1. A copy of the FPP Deferred Submittal application
  2. Three (3) sets of plans
  3. Two (2) set of calculations
  4. Two (2) sets of product information
  5. Drawings and calculations must be stamped and signed by an Engineer registered in Oregon and approved by the Architect/Engineer of record for the building. If one or both are not on plans, they will not be accepted for review
  6. Complete project submittals may be made to Permitting Services
    1900 SW 4th Ave, 2nd floor (Mon – Fri 8 a.m. to 3 p.m. and Thurs 8 a.m. to Noon)

Revision:

  1. A copy of the FPP Revision application
  2. Three (3) sets of plans that clearly reflect the proposed change(s). Drawings and calculations must be stamped and signed by the Architect and/or the Engineer of Record, if applicable
  3. Two (2) sets of calculations, if applicable
  4. Inspector’s correction notice, if revision is due to an inspection correction
  5. Complete project submittals may be made to Permitting Services
    1900 SW 4th Ave, 2nd floor (Mon – Fri 8 a.m. to 3 p.m. and Thurs 8 a.m. to Noon)