Fremont Pump Station

Updated May 10, 2019Button. Click to sign up for email updates

Environmental Services is constructing upgrades to the almost 40-year-old Fremont Pump Station, a sewage pump station located on NE Fremont Drive near NE 89th Avenue. While the pump station structures will largely remain unchanged, aside from new roofing and minor repairs, the pumping system will be upgraded. The improvements will replace aging equipment, ensure safe and reliable operations, and meet current noise and odor control standards.

Click here for details about the pump station improvements. This project will help to ensure the pump station operates safely and efficiently to protect public health, water quality, and the environment.

Schedule

Construction will go through several phases and is anticipated to be completed in October 2019.

Typical work hours are from 7 a.m. to 6 p.m. Monday through Friday, with construction on Saturday if needed.

Project Map

Fremont Pump Station project map

Upcoming Activities

The City’s contractor, Stettler Supply Company, continues to work on-site at the Fremont Pump Station. Over the next few months, the contractor will focus on the following activities:

  • Complete installation of new electrical equipment (panels, conduits, and conductors)
  • Complete exterior concrete work for the heating, ventilation, and air conditioning systems
  • Complete installation of exterior sound trap
  • Install the new heating, ventilation, and air conditioning units
  • Install new low voltage motor control center
  • Install new pump

A temporary bypass pumping system is in place and operating properly. It will continue to operate until the upgrade project is completed. It is diverting combined sewer and stormwater flows to other parts of the sewer system. These pipes have the capacity to handle increased flows while the pump station upgrades are under construction.

Click here for more details about what to expect during construction.

Project Accomplishments To Date

Major project accomplishments to date include the following:

  • Demolished the existing mechanical, electrical, and plumbing equipment
  • Installed equipment for pump station cleaning and maintenance
  • Installed equipment that will provide accurate, ongoing flow measurement
  • Completed most of the concrete work for the foundation, generator pad, and sound trap pads
  • Completed epoxy coatings in the wet well and flow meter vault
  • Installed new structural steel in the dry well
  • Completed all major pipe installations

For More Information

If you would like more information about the project or have questions and concerns you’d like to discuss, please call or email:

Cheryl Kuck
Community Outreach
Phone: 503-823-7898
Email: Cheryl.Kuck@portlandoregon.gov

If you have a concern or question about the project, please be sure to include your name, property address, and project name (Fremont Pump Station) in your voicemail and email so we can provide you more details about what to expect in front of your property. Also, please write "FremontPS" in the subject line of your email. Click SIGN UP to sign up for periodic email updates. Let us know if you have concerns such as business operations, disability issues, medical or business deliveries, or other neighborhood impacts.


Project Overview

Including the project description, map and schedule

Community Outreach

Check out current and previous communications about the project