Skip to Main Content View Text-Only

Environmental Services

working for clean rivers

Phone: 503-823-7740

Fax: 503-823-6995

1120 SW 5th Avenue, Room 1000, Portland, OR 97204

More Contact Info

Woodlawn-King Alleys

Updated June 19, 2017

As soon as Thursday, June 22, concrete street restoration will limit alley access in multiple locations indicated on the map below.

  • Preparation for concrete street restoration is currently scheduled to occur on Thursday, June 22. This work may be postponed due to weather or subcontractor availability and rescheduled on short notice.
  • Crews will then remove temporary asphalt patches and restore the trenches with concrete. Once the concrete is poured, it will take up to seven days to harden to the required strength for car and truck traffic.
  • For a minimum of three days following the concrete pour, there will be limited local access, then the area will be plated while the concrete continues to harden.

Crews will continue spot repairs, cleanout installation, and lateral sewer pipe construction in multiple locations indicated on the map below.

  • These smaller phases are being completed to prepare for Cured in Place Pipe Lining (CIPP) sewer repairs later this summer.
  • The contractor will apply temporary pavement to all areas excavated for sewer construction. Final trench paving and concrete restoration work throughout the project area will occur as crews become available.

Please be aware that schedules are subject to change due to a variety of factors, including conditions underground, weather, traffic impacts and subcontractor and materials availability. Residents and businesses should expect periods of inactivity between each phase ranging from a few days to a few weeks. The duration depends on a variety of variables including underground conditions, weather, traffic impacts, subcontractor schedules, quality control tests and availability of materials. To learn more about visit the What to Expect During Construction page.

Construction ScheduleConstruction Locations

This project is expect to run until summer 2018.

Construction will move from one site to another as work phases are completed, with periods of inactivity between phases. Please be aware that schedules are subject to change due to a variety of factors, including conditions underground, weather, traffic impacts and subcontractor and materials availability.

Construction Hours

Construction hours are from 7:00 a.m. to 6:00 p.m. Monday through Friday, but the contractor may schedule work during the same hours on Saturdays. The Portland Noise Office approved night work for two locations within the project boundaries. (This work is not in the current schedule.) Homes and businesses near these locations will receive a separate notification before night work takes place. Check the project map for night work
locations.

Construction Methods

Sewer pipe repair or replacement will be completed using a combination of open trench and trenchless construction methods. To see photos and learn more about the construction methods indicated on the map, go HERE.

Let Us Know

Do you have problems with water seeping into your basement? Please let Environmental Services know by taking the online basement moisture survey. Survey responses help identify neighborhoods with seepage problems and design stormwater management projects.

  


Stay Informed

Sign up for email updates and other project notifications

Community Outreach

Check out upcoming public meetings, and current and previous communications about the project

Project Overview

Including the project description, map and schedule