Alder Pump Station

Updated November 14, 2017

Button. Click to sign up for email updatesEnvironmental Services will soon begin demolition of the Alder Pump Station as part of the Alder Pump Station Upgrade Project. The city constructed the pump station at SE Water Avenue and SE Alder Street in 1952. This upgrade project will improve reliability, increase pumping capacity, and help prevent sewage releases to protect public health, water quality, and the environment. For details about the improvements to be made, click here.

Schedule

Construction of upgrades will go through several phases and take up to two years to complete. Typical work hours will be 7 a.m. to 6 p.m. Monday through Friday, with construction the same hours on Saturday if needed.

Project map

Developments of Note and Upcoming Activities

Demolition of the pump station is scheduled to begin this Friday, November 17, at 7:30 a.m., and will continue through mid-December.

This work will be done in phases:

  • Crews will begin by sawcutting the roof to enable the removal and salvage of parts.
  • After the Thanksgiving holiday, crews will demolish the walls and outside structure.
  • The entire aboveground structure of the pump station is expected to be down by the end of December.
  • Some additional demolition may continue below ground in January 2018.

The city's contractor installed and tested a bypass pumping system last week:

  • This bypass system will ensure continued sewer service throughout the project when the pump station is taken off line for construction of the upgrades.
  • During construction, combined sewer and stormwater flows will be diverted to other parts of the sewer system. These pipes have the capacity to handle increased flows while the new pump station is under construction.

Anticipated Traffic Controls

Different phases of this project may require different traffic controls as upgrades on the site and frontage improvements in the public right-of-way are completed. The general traffic control plan is as follows:

  • Allow access to private driveways at all times
  • Employ flaggers to direct bicyclists away from the work area but not into the flow of motor vehicle traffic and to direct pedestrians to safe crossings and open sidewalks
  • Establish traffic controls so that traffic queues do not extend into the railroad track zones
  • Maintain a one-way, westbound travel lane on SE Alder Street to SE Water Avenue
  • Maintain two-way traffic on SE Water Avenue
  • Remove on-street parking in the work zone

For More Information

If you would like more information about the project or have questions and concerns you’d like to discuss, please call or email:

Cheryl Kuck
Community Outreach
Phone: 503-823-7898
Email: Cheryl.Kuck@portlandoregon.gov

If you have a concern or question about the work near you, please be sure to include your name, business name, property address, and project name (Alder Pump Station) in your voicemail and email so we can provide you more details about what to expect in front of your property. Also, please write "AlderPS" in the subject line of your email. Click SIGN UP! to sign up for periodic email updates, and select Alder Pump Station Upgrade Project from the dropdown menu.


Project Overview

Including the project description, map and schedule

Community Outreach

Check out current and previous communications about the project

Stay Informed

Sign up for email updates and other project notifications