Skip to Main Content View Text-Only

The City of Portland, Oregon

Environmental Services

working for clean rivers

Phone: 503-823-7740

Fax: 503-823-6995

MAILING ADDRESS: 1120 SW 5th Ave, Room 1000, Portland, OR 97204

More Contact Info

Hillsdale Sewer Repair Project

Updated June 29, 2018Button. Click to sign up for email updates

Environmental Services is designing projects in the Hillsdale and Multnomah neighborhoods of Southwest Portland to repair or replace 30,000 feet, or 5.7 miles, of public sewer pipes that are on average 80 years old and in deteriorating condition. Project design is currently focused on 9,000 feet, or 1.7 miles, in the South section.

The project will also install new manholes and storm drain inlets where needed, repair existing manholes and storm drain inlets, and replace some public sewer connections to private properties from the main line in the street to the curb. This investment in your neighborhood will ensure continued dependable sewer service and protect the public and our environment by reducing the possibility of sewage releases to homes, businesses, and streets.

Project Area

The project area is divided into three sections, as shown on the map, and will be completed in phases. Project design is currently focused on the South section, which will include about 9,000 feet, or 1.7 miles, of sewer pipes.

Hillsdale project boundary map

Hillsdale South Section map

Schedule

Design in the South section will continue through 2018. A construction contractor will be selected in early 2019. Construction in the South section only is anticipated to begin in the summer of 2019 and take up to a year and a half to complete.

Design and construction timelines for the Middle and North sections are not yet known. They will be done sometime after the South section.

Design Update

Over the last few months, crews have been in the neighborhood surveying, locating utilities, inspecting sewer pipes and manholes, studying soil types and conditions, and collecting information to help engineers decide which locations need repair and what construction methods are best for each location. You may still see crews in the neighborhood conducting these activities.

These design and pre-construction activities typically occur over time, rather than all at once.

Proposed Night Work

Environmental Services is partnering with the Portland Bureau of Transportation to complete sewer repairs on Capitol Highway as part of their repaving project. Work at each of the three locations (see map) should take less than one week and require one night of work at each location, with daytime pipe cleaning and sewer bypass setup.

Environmental Services is proposing to work 24/7 for approximately one day and night to line the sewer pipes. The pipe lining process is a minimum 24-hour process and cannot be stopped once started. Nighttime construction on Capitol Highway is expected to occur sometime between August 2018 and February 2019. The specific dates for this day and night work will be determined after a city contractor is hired to do the work.

Portland noise code allows construction from 7 a.m. to 6 p.m. Monday through Saturday. Work after 6 p.m. and before 7 a.m. and all hours on Sundays requires a noise variance from the Portland Noise Office. Because construction crews will work past 6 p.m. one day and night to line the pipes and harden the lining, Environmental Services will apply for a noise variance. Equipment that generates noise will include a water jet truck, sewer cleaning truck, air compressor, sewer bypass pumps, generators, front end loader, and crane. Night work will require lights.

Submit Comments to Portland Noise Office

Your comments about the proposed noise variance are valuable and can be submitted to the Portland Noise Office by letter, email, or telephone. Please submit your comments by June 29 to:

Portland Noise Office
1221 SW 4th Avenue, Suite 110
Portland, OR 97204
Email: noise@portlandoregon.gov
Phone: 503-823-7350

For More Information

If you would like more information about the project or have questions and concerns you’d like to discuss, please call or email:

Cheryl Kuck (Joe Tursi is on paternity leave through July 13)
Community Outreach
Phone: 503-823-7898
Email: Cheryl.Kuck@portlandoregon.gov

If you have a concern or question about a pipe repair near you, please be sure to include your name, property address and project name (Hillsdale) in your voicemail and email so we can provide you more details about what to expect in front of your property. Also, please write "Hillsdale" in the subject line of your email. Click SIGN UP to sign up for periodic email updates.


Project Overview

Including the project description, map and schedule

Community Outreach

Check out current and previous communications about the project