Skip to Main Content View Text-Only

The City of Portland, Oregon

Environmental Services

working for clean rivers

Phone: 503-823-7740

Fax: 503-823-6995

MAILING ADDRESS: 1120 SW 5th Ave, Room 1000, Portland, OR 97204

More Contact Info

NE Argyle Drive Sewer Repair Project

Updated January 2, 2019Button. Click to sign up for email updates

Environmental Services plans to begin construction in mid-January to repair 40 feet of public sewer pipes and replace two manholes in NE Argyle Drive east of NE 11th Avenue. The pipes and concrete manhole are severely deteriorated from sanitary sewer flows and sewer gases. This project will line the pipes and install two corrosion-resistant manholes. These improvements will help protect public health, water quality, and the Columbia Slough Watershed. 

Location

The map below illustrates where sewer repairs will be constructed.

Project map

Schedule

Construction is anticipated to begin in mid-January. Once construction begins, work is expected to take about one month to complete.

Northeast Argyle Drive is one of three locations where the city’s contractor will be working. The others are N Interstate Place at N Argyle Street and N Marine Drive between N Portland Road and N Force Avenue. The contractor plans to work on Argyle Drive first, before moving to the other locations.

Below is the general schedule for work at the NE Argyle Drive location:

  • January 11 - February 7 – Set up and keep in service the sewer bypass/flow diversion system
  • January 11-17 – Prepare pavement for manhole replacement
  • January 17 – Sawcut pavement for manhole replacement
  • January 18-31 – Install two new manhole inserts
  • February 1-4 – Conduct the spot repair
  • February 5 – Line the sewer pipe and cure the lining
  • February 6-8 – Complete sewer pipe and manhole repairs
  • February 7 - Conduct post-construction video inspection of the sewer pipe
  • February 7 - Remove the sewer bypass/flow diversion system
  • February 11 – Restore street pavement disturbed by construction

Note that this schedule could change depending on weather, subcontractor schedules, availability of materials, and other factors.

James W. Fowler Co., the contractor for this project, will provide notice in advance of construction.

Work Hours

Work will occur 7 a.m. to 6 p.m. Monday through Friday, and the same hours on Saturday as needed.

Construction Methods

This project will use both trenchless and open-cut trench construction methods to repair the sewer pipes and replace the manholes.

To repair the sewer pipes, the city will employ a method called cured-in-place-pipe lining (CIPP). Work crews access the sewer from manholes to insert a flexible liner inside the old pipe. Ultraviolet rays will cure the liner, which gradually hardens to form a rigid, smooth surface that seals cracks and restores the pipe to near-new condition. This method of using ultraviolet rays to cure the liner does not have the odor typically associated with CIPP lining work that uses water or steam to cure the liner.

CIPP is generally a three-day process to set up the bypass service, line the pipe, and reinstate sewer connections to buildings.

It might also be necessary for crews to do a small spot repair to a section of sewer pipe that is approximately 15 feet deep and directly underneath a 66-inch pipe that carries just stormwater. Avoiding digging here is the preferred solution, but if the lining operation is not effective at this point in the pipe, crews will have to dig a trench to replace this five-foot section of sewer pipe.

Crews will replace the two deteriorated manholes with corrosion-resistant manholes. It will be necessary to dig a pit to install each manhole.

Permanent pavement restoration will be made after the pipe and manhole improvements are constructed.

For more information and photos about construction methods, click here.

Traffic Controls

This project will require temporary traffic diversion during construction. Access to driveways and properties will be provided at all times, although there may be delays. The goal will be to maintain a 12-foot-wide traffic lane with two-way traffic controlled by two flaggers, one at each end, during work hours.

For More Information

If you would like more information about the project or have questions and concerns you’d like to discuss, please call or email:

Cheryl Kuck
Community Outreach
Phone: 503-823-7898
Send an email

If you have a question or concern, please include your name, business name, property address, and project name (NE Argyle Dr) in your email and voicemail. Also, please write "NE Argyle Dr" in the subject line of your email. Click SIGN UP to sign up for periodic email updates.


Project Overview

Including the project description, map and schedule

Community Outreach

Check out current and previous communications about the project