Skip to Main Content View Text-Only

Environmental Services

working for clean rivers

Phone: 503-823-7740

Fax: 503-823-6995

1120 SW 5th Avenue, Room 1000, Portland, OR 97204

More Contact Info

Project Overview

In the spring of 2017, Environmental Services completed Phase One of a project to repair 100 to 140-year-old public sewer pipes in SW Yamhill and SW Morrison Streets in downtown Portland that were in deteriorating condition. The sewer pipes were showing signs of cracks, breaks, holes, offset pipe connections, and root and grease obstructions, putting the pipes at risk of structural failure.

Work is continuing now through November 2017 on Phase Two to repair another 2,700 feet (0.5 mile) of public sewer pipes in areas that were identified as high risk, where crews were not able to safely bypass sewage flows from adjacent properties to repair the public sewer in the street this past spring. The three-week light rail closure wasn't enough time to complete that challenging work. Environmental Services is back in contact with those properties to discuss and plan repairs to take place this fall at the locations shown in the map below.

Project Map

Project map - continuing work

Schedule

Sewer repairs will continue at the above locations through November 2017 and perhaps even in early 2018. Construction hours may vary throughout the project, with some work to take place after 6 p.m. and before 7 a.m. to reduce traffic congestion, create a safer work zone, and allow time for the new sewer pipe lining to harden.

Project Accomplishments - Spring 2017

Environmental Services set out to do a large-scale sewer repair project in a short amount of time. TriMet’s MAX Improvement Project gave us the rare chance to work on underground sewer pipes that cannot be accessed while overhead high-voltage power lines are live and light rail trains are running.

In the three weeks that light rail was out of service, the city’s contractor was able to accomplish the following repairs and address immediate needs to extend the life span of sewer pipes in the project area:

  • Inspected 4,500 feet (0.85 mile) of mainline public sewer pipes and service laterals
  • Cleared roots and flushed debris from approximately 4,500 feet (0.85 mile) of public sewer pipes and service laterals
  • Installed 3,200 feet (0.6 mile) of cured-in-place-pipe lining to repair mainline public sewer pipes
  • Investigated over 30 public service laterals to locate where adjacent buildings are connected to the mainline public sewer
  • Installed 25 sewer cleanouts to provide bypass sewer service during the pipe lining process and to provide access for future sewer maintenance activities

While the majority of the project was able to be accomplished in the short time period, some future work will be necessary to ensure high quality infrastructure for our community, including:

  • Repairing mainline public sewer pipes in challenging locations not repaired with this project
  • Determining how to bypass sewer flows in challenging locations for future repairs
  • Repairing public service laterals to adjacent buildings on SW Yamhill and SW Morrison Streets
  • Working with private properties to determine potential private plumbing modifications necessary to complete public sewer repairs