Skip to Main Content View Text-Only

The City of Portland, Oregon

Office of Management & Finance

Bureau of Revenue and Financial Services

Phone: 503-823-5288

Fax: 503-823-5384

1120 SW 5th Avenue, Rm 1250, Portland, OR 97204

BOP Project Clearinghouse
PTE | Construction | Technology  
 
Project Forecast Calendar: Construction

The following project calendar represents formal City of Portland construction projects expected to be released during the next 3-6 months. While efforts will be made to keep information on this page current, please note that not all City construction projects may be displayed on this page prior to issuing a solicitation and changes may be made to project plans at any time. For project specific questions, call the project contact person listed below.

To view current City contract opportunity solicitations and receive notices as solicitations are issued, please make sure to register as a vendor with the City's online solicitation system at: procure.portlandoregon.gov/bso/

 

From   To 
View 
Click column header to sort by that column
City of Portland - Environmental Services  
Project Title/Description WBS Bureau Element Project Estimate Funding Source Est. Project Release Date Contact Person Phone Scope Entry Created Entry Updated
Balch Creek Trash Rack Retrofit E10583 $1,475,800.00 Local 02/19/20 LastoMirsky, Chris 503-823-5489 Capital maintenance of existing trash racks adjacent to the Lower Macleay trail in Forest Park. These large structures and bays keep the majority of sediment, rock, and floating debris from entering the low pressure storm sewer that conveys Balch Creek from Forest Park (near NW 30th & Thurman) to the Willamette River at Outfall 17. 11/09/2018 09:11 01/08/2019 09:01
CBWTP Dig 9&10 Transfer Pumps REPL E11113 $608,000.00 Local 05/28/19 McKenna, Heather 503-823-6900 Replace existing sludge transfer pumps at CBWTP Digesters 9 and 10 with centrifugal pumps. 09/11/2018 14:09 01/08/2019 09:01
CBWTP Effluent PS VFD Cooling Project E11051 $751,143.37 Local 02/21/19 Coker, Jenny 503-823-2689 Effluent Pump Station VFD Cooling Improvements 01/08/2019 09:01 01/08/2019 09:01
CBWTP WWCL Structural Rehab E11118 $4,759,463.70 Local 04/02/19 Wilson, Derek 503-823-2499 The goal of this project is to assess the nature and extent of the damage to the tanks and rehabilitate the concrete surface to ensure continued operation and prevent future outages and repairs. 11/09/2018 13:11 01/08/2019 09:01
DTOT Salmon-Taylor Sewer Rehab E10999 $6,691,200.00 Local 03/13/19 Hjorten, Susan 503-823-7098 Downtown-Old Town Salmon-Taylor Sewer Rehab from SW Naito to I-405 01/08/2019 09:01 01/08/2019 09:01
Errol Heights Stormwater LID E10917 $2,332,583.00 Local 05/22/19 Wilson, Brandon 503-823-7786 LID in Errol Heights to improve streets and add stormwater infrastructure. 08/01/2018 11:08 01/08/2019 09:01
Fiber Expansion for Inverness PS E11158 $1,861,000.00 Local 07/01/19 Chadburn, Roland 503-823-2846 This project request will install additional components to make that network more complete and robust. 01/08/2019 09:01 01/08/2019 09:01
Hillsdale Crest RDII E10941 $6,800,000.00 Local 03/26/19 Young, Henry 503-823-7278 This project will address the implementation of sewer improvements to control the DeWitt SSO within the Burlingame Basin. 04/02/2018 10:04 01/08/2019 10:01
Ladd's Addition South Recon/GRST E10369 $4,383,100.00 Local 07/08/19 Word, Tressie 503-823-2926 Construct improvements to rehabilitate pipe segments that are in poor condition, upsize pipe segments and install street, roof and parking stormwater controls to relieve street flooding and basement sewer backups. Located in SE Portland, the project area is generally bound by Market, 20th, Division, and 12th. 01/08/2019 10:01 01/08/2019 10:01
Luther Rd. Restoration (FEMA) E10854 $ 1,570,816.00 Local 02/27/19 Lastomirsky, Chris 503-823-5489 Geomorphic & habitat assessment 09/11/2018 15:09 01/08/2019 10:01
N Commercial and N Shaver Sewer Rehab E11092 $357,000.00 Local 02/28/19 Chan, Terence 503-823-7087 Rehabilitate the existing 12" sewer main and laterals 09/11/2018 15:09 01/08/2019 10:01
NE 29th NE Hancock SW Barbur Sewer Rehab E11120 $1,219,300.00 Local 05/21/19 Chan, Terence 503-823-7087 Sewer rehab for three separate pipe segments 12/03/2018 10:12 01/08/2019 10:01
NE Broadway & 94th PS Upgrade E10783 $2,024,400.00 Local 04/29/19 Nguyen, Huong 503-823-2625 The project is to upgrade the pump station to improve reliability and maintenance. 06/04/2018 09:06 01/08/2019 10:01
NW Northrup Sewer Rehabilitation E11127 $952,886.96 Local 05/22/19 Boatman, Daniel 503-823-7162 Rehab approx 100 ft of 16" VSP along NW Northrup from 21st to 23rd Ave next to street car tracks and hospital buildings. Construct lateral cleanouts and line or burst defective laterals. 12/03/2018 10:12 01/08/2019 10:01
Portsmouth FM Valve Vault Level Mntrng E10735 $327,708.00 Local 02/22/19 Thompson, Clarence II. 503-823-2623 Rehabilitate and downsize the existing combined sewer main. 11/09/2018 15:11 01/08/2019 12:01
S Portland - Burlingame Sewer Rehab Ph1 E10680 $3,518,266.40 Local 04/01/19 Boatman, Daniel 503-823-7162 Rehabilitate / replace of small diameter severely deteriorated public sewer, some manhole replacement, and some public lateral replacement, in the Hillsdale area of SW Portland. 09/11/2018 15:09 01/08/2019 12:01
Slough Outfall 100 E10689 $2,487,600.00 Local 04/09/19 Leis, Patrick 503-823-7377 This project is for the design and construction of stormwater treatment facilities to treat stormwater runoff from City ROW in outfall basin 100. The basin contains 25 acres of COP ROW. 09/11/2018 15:09 01/08/2019 13:01
SLRT Monitoring Upgrades FY 16 & 17 E10743 $347,000.00 Local 04/10/19 Thompson, Clarence II. 503-823-2623 Scope: Replace the existing SLRT Monitoring Panels at nine locations with new SLRT panels. Add a radar flow sensor at one of the nine locations. Replace existing retaining wall surrounding a SLRT panel at a tenth location. Objective: to modernize HYDRA data collection for the City sewer system in order to prevent CSO events. 03/07/2018 10:03 01/08/2019 13:01
SW Woods W of SW 2nd E11124 $210,300.00 Local 05/22/19 Russell, Margaret 503-823-5327 Evaluate, rehabilitate and possibly upsize 145FT of 85yr old VSP combined sewer. 12/03/2018 11:12 01/08/2019 13:01
SW Yamhill/Morrison Phase 3 E11148 $702,000.00 Local 04/30/19 Hjorten, Susan 503-823-7098 CIPP 5 mains and 6 laterals 01/08/2019 13:01 01/08/2019 13:01
TCWTP Disinfection Improvements Phase 1 E11112 $1,137,175.05 Local 08/27/19 McKenna, Heather 503-823-6900 Improve disinfection treatment process at TCWTP. 10/02/2018 13:10 01/08/2019 13:01
TCWTP Headworks Improvements E10582 $57,022,419.00 Local 08/13/19 Coker, Jenny 503-823-2689 The TCWTP Facilities Plan Update is nearly complete and has identified key improvements. These improvements are driven by a need to bring the headworks process up to current treatment and efficiency standards, increase peak flow hydraulic capacity, community needs, and an opportunity to improve the plant hydraulic profile. 12/03/2018 11:12 01/08/2019 13:01
City of Portland - Transportation
Project Title/Description WBS Bureau Element Project Estimate Funding Source Est. Project Release Date Contact Person Phone Scope Entry Created Entry Updated
Connected Cully T00460 $1,800,000.00 04/08/19 Roske, Kim 503-823-5183 Grading, Paving, Concrete Flatwork, Drainage, Signing, Striping, Roadside Development 01/08/2019 16:01 01/09/2019 10:01
Greeley Multi-Use Path T00696 $1,200,000.00 03/15/19 Roske, Kim 503-823-5183 Grading, Paving, Concrete Flatwork, Drainage, Signing, Striping, Roadside Development 01/09/2019 10:01 01/09/2019 10:01
N Burlington and N Edison T00686 $600,000.00 LID 04/09/19 Joe, Jimi 503-823-7564 Grading, Paving, Concrete Flatwork, Drainage, Signing, Striping, Roadside Development 01/09/2019 11:01 01/09/2019 11:01
SE 80th Ave and SE Mill St T00728 $1,600,000.00 LID 03/09/19 Joe, Jimi 503-823-7564 Grading, Paving, Concrete Flatwork, Drainage, Signing, Striping, Roadside Development 01/09/2019 11:01 01/09/2019 11:01
SW 47th Ave - Lauradel - LID T00656 $250,000.00 LID 03/09/19 Joe, Jimi 503-823-7564 Street improvements and stormwater sewers. 01/09/2019 12:01 01/10/2019 09:01
Page Views: 1386714