Processes & Forms Implementation Timeline

PHASE

START DATE

Project Begins

October 5, 2015

Blueprinting

October 12, 2015

Realization Phase

December 7, 2015

System Integration Testing

February 29, 2016

User-Acceptance Testing

March 21, 2016

End-User Training

April 11, 2016

Project Go-Live PILOT Bureaus

June 1, 2016

Project Go-Live ALL Bureaus

June 15, 2016

Project Ends

July 1, 2016

Project Phase II – Out of Scope Forms

January 2017