Construction Update: May 2019
Things are moving quickly on the construction front with trade crews working on all floors of the Portland Building. Framing of the basement support spaces has been completed, including the locker room, group exercise room, and the fitness center. The tenant space on the fourth floor is close to completion with restroom partitions and gathering room casework currently being installed and furniture delivery in process. Floors five, six, and seven are not far behind the fourth. Floors eight through fifteen are in various stages of build-out including mechanical systems, restroom plumbing, tile work and framing, drywall, and painting of interior spaces.
The exterior has seen the last curtain wall panel installed and the medallion and ribbon details are in place on the north and south façades.
Keep an eye out this month for the installation of the capitals on the west side over Portlandia and the removal of the tower crane!
Construction pictures (restroom doors! gathering space! locker room framing!) here.