Kenton Park

Kenton Park Playground - BEFORE

Project Update

Read the latest project update here. Construction will occur in Summer 2018, with completion by Fall 2018.

Perspective of playground

Plan for Playground

Project Overview

Outdated, inaccessible play structures, picnic tables, benches, a drinking fountain, and paved paths will be replaced in the playground area at Kenton Park, thanks to funding from the Parks Replacement Bond. Parks will also be making minor restroom improvements for ADA accessibility as a separate project. 

Project Manager
Gary Datka,, (503) 823-5574

Public Involvement Coordinator
Maija Spencer,, (503) 823-5593

Project Timeline

  • Winter 2017 - Spring 2017: Concept Development and Public Involvement
  • Summer 2017: Construction Documents
  • Fall 2017:  Permitting
  • Winter 2017/18: Bidding
  • Spring / Summer 2018: Construction
  • Fall 2018: Re-opening of playground!

Project Updates

To receive project updates, sign up here.