PROJECT OVERVIEW

Thanks to the passage of the Parks Replacement Bond, funds are available to renovate the restrooms at Bloomington Park, including demolishing walls, re-configuring interior walls to provide ADA-compliant restrooms, installing new plumbing and fixtures, and improving roof drainage. The existing restrooms will become two all user restrooms with single occupancy.

Additional ADA improvements include replacing the pathway between the playground and SE Steele to provide an ADA-compliant route and the addition of signage and a curb cut for a reserved ADA parking space on SE Steele. 


Project Manager
Evan Callahan, evan.callahan@portlandoregon.gov, (503) 823-2528

Public Involvement Coordinator
Maija Spencer, maija.spencer@portlandoregon.gov, (503) 823-5593


PROJECT SCHEDULE

Spring 2016 - Summer 2016
Design Development

Summer 2016 - Spring 2017
Construction Documents, Permitting, and Bidding

July 2017 - Winter 2017
Construction


PROJECT UPDATES

Construction will begin on Tuesday, July 18, 2017. During that time, the restrooms will be closed for use. A porta-potty will be provided for the public's use.