Most Recent

View More

Gateway Green

  • Concept drawing - Gateway Green

This 25-acre site is located just east of Rocky Butte at the intersection of the I-205 regional trail and the future Sullivan’s Gulch Trail, and the confluence of two major freeways. The construction of I-205 and I-84 created this previously unused remnant of land with a complicated set of public access challenges. 

DEVELOPING GATEWAY GREEN, PORTLAND'S FIRST BIKE PARK.

Gateway Green offers off-road cycling trails and a mountain-biking destination in East Portland. The Dirt Lab, featuring bike trails, a pump track and bike skills area, opened to the public in June 2017.

The park is currently under construction and in development. Improvements to make the site fully accessible and ADA compliant do not yet exist. Please use your personal discretion to visit the site under current conditions. Click here for park hours and visitor rules.


Access

This park is car free! Walkers and bicycle riders can reach the site via the I-205 multi-use path, or ride MAX and buses to the Gateway Regional Center and follow the multi-use path north for about a half mile to the park entrance. 


Overview

Gateway Green will provide a much-needed site for off-road cycling, and other outdoor recreation in East Portland. A system of trails, both soft-surface and paved multi-use trails, will allow visitors to explore the unique site and connect to the regional trail and cycling network.

A plan is needed to guide future work to restore habitat, improve access, and enhance other recreational activities at Gateway Green. You are invited to participate in shaping a community-supported design for the park.

Planning to create a comprehensive design and master plan will begin in late summer 2017. The park design will include active recreation and off-road cycling features, habitat restoration and enhancement, as well as public access and utility improvements.

Friends of Gateway Green (FoGG) is a key partner, and will manage programming at the developing park. PP&R will work collaboratively with FoGG, Metro, and other partners to engage diverse communities as we create this innovative bike park.


Background

In 2014, the Metro Council awarded FoGG a $1 million Nature in Neighborhood capital grant, and Portland Parks & Recreation purchased the property from the Oregon Department of Transportation.

Community leaders and advocates were instrumental in the development of this park. Robust support is provided by a highly visible and active group – Friends of Gateway Green. The Gateway Green Vision Plan (2008) was developed through a two-year community-led effort funded by residents and advocates.

The park site has been the focus of several previous planning efforts:

  • PP&R Feasibility Study (2015),
  • FoGG Concept Design (2010),
  • East Portland Action Plan (February 2009),
  • Gateway Green Vision Plan (May, 2008), and
  • Site inventory conducted by Portland State University Master of Urban and Regional Planning graduate students (2006). 

Construction Schedule

There are three phases of construction in this project to maximize the habitat restoration efforts and minimize the risks associated with the limited access. The first phase was completed in June 2017.

Phases Two and Three will occur between Summer 2017 and 2019.

Completed in June 2017

  • Phase One -- Construction of Dirt Lab, mountain-biking, and cycling features.

Summer 2017 -- Spring 2019

  • Phase Two – Install utilities at the south end of the park, and continue invasive plant removal.
  • Phase Three -- Implement park features including site grading, and multi‐use path
    • Plant / Habitat Restoration
    • Multi‐use Trail
    • Site Grading and Earthwork
    • Entry Plazas
    • Natural Play Features

Budget: $3 Million

Funding Sources:  $1M Metro IGA, and $2M Parks & Recreation System Development Charges

Design Consultant:  Greenworks, PBS Engineers