Springwater Connector Neighborhood Greenway

Click map for a larger version

What's Happening Now?

The project is currently moving through engineering design. Design is expected to wrap up by the end of summer.

Project Background

PBOT has been developing Neighborhood Greenways to connect neighborhoods, schools, parks, jobs, commercial centers, transit and other destinations in the City of Portland.  The Springwater Connector project will connect the 70's and 80's greenways with the Springwater Trail.

Proposed project elements include:

  • Pavement markings (sharrows)
  • Wayfinding signs
  • Speed bumps
  • Tree planting

Project Timeline: The design phase of this project kicked-off in summer of 2018. Construction should begin in summer of 2020 and wrap up in the fall of 2020.

Project Phase: Design

Project budget: $552,000 from Fixing Our Streets and other funding from Transportation System Development Charges 

Project Manager Contact Information:

David Backes

David.Backes@portlandoregon.gov 

503-823-5811

Last updated 2 April 2019