The project is completing final design and moving to construction in the Fall of 2019.
The project will construct a new bridge to elevate North Rivergate Blvd over the Union Pacific RR tracks crossing the roadway. Currently rail operations block North Rivergate Blvd for long time periods causing traffic congestion affecting one of the region’s largest industrial area. In 2016 the Port of Portland received a grant from the U.S Department of Transportation’s TIGER program to construct an overcrossing on N. Rivergate Blvd. The project has also received funding from Metro, the Oregon Department of Transportation and City of Portland Transportation System Development Charges.
Construction begins: Will begin construction in October 2019
North Rivergate Blvd closes to traffic: Anticipated March 16, 2020
North Rivergate Overcrossing opens: Anticipated Spring 2021
Project Complete: Spring 2021
*During construction, North Time Oil Road will be used as a detour*
Project Cost: $25.8 Million
Project Manager: Dan Layden, (503) 823-2804 dan.layden@portlandoregon.gov