Halsey Street Safety and Access to Transit

Project Description:
- Pedestrian and bicycle improvements between NE 80th and 92nd Avenue
- NE 80th Avenue to Jonesmore Street – two-way buffered bike lanes
- NE Jonesmore Street to 92nd Avenue - two-way multi-use path on south side of Halsey
- Improve/widen existing multi-use path connection from NE 82nd MAX station to 81st Avenue
- Crossing improvements at NE Halsey and:
- 68th Avenue/69th Avenue
- 80th Avenue
- Jonesmore Pl/84th Avenue
- 88th Avenue
- Sidewalk infill at NE Halsey Street and 80th, 85th, and 88th avenues
- Update curb ramps to ADA standards
- Bus stop improvements
- Lighting analysis, add lighting if needed
Schedule:
Begin design – January 2020
Begin construction – Fall 2021
Contact Info:
Nicole Peirce, Capital Project Manager
nicole.peirce@portlandoregon.gov