CONSTUCTION UPDATES
Construction Schedule:
Construction is anticipated to begin on November 17, 2011 with completion by April 6, 2012
THREE WEEK SCHEDULE
Location |
Improvements |
Activity |
Traffic Control |
Week Jan 16-20 |
Week Jan 23-27 |
Week Jan 30 -3 |
Reno/ Lombard |
Median |
|
|
|
|
|
St Louis/ Lombard |
Corner radius Signal |
|
|
|
|
x |
St Louis/ Ivanhoe |
Corner radius |
foundations |
|
|
|
|
New York/ Ivanhoe |
Curb extensions |
Erosion control |
1 |
|
x |
x |
Baltimore/Ivanhoe |
Signal |
Erosion control foundations |
1/2 |
x |
x |
x |
Philadelphia/ Ivanhoe |
Corner radius |
Erosion control |
|
|
|
|
Leavitt/ Lombard |
Curb extensions |
|
|
|
x |
x |
Leavitt/ Ivanhoe |
Curb extensions |
Erosion control |
|
x |
x |
x |
John/ Ivanhoe |
Curb extensions |
|
|
x |
|
x |
Charleston/Ivanhoe |
Curb extensions |
|
|
|
x |
|
Richmond/Ivanhoe |
Signal |
foundations |
|
|
|
|
Notes: 1: parking restriction 2: lane closure All construction activity scheduled is subject to weather |