NE 52nd Avenue and Alberta Street LID
LID formed by City Council on April 3, 2013
Design completed on April 29, 2014.
Click Here for construction plans
Advertised for bids on May 19, 2014.
Opened bids on June 12, 2014.
Executed contract with Kodiak Pacific Construction, Inc. on July 31, 2014.
Issued Notice to Proceed to Kodiak Pacific Construction, Inc. on August 25, 2014.
Paving completed on September 22, 2014 with speed bumps installed on September 25, 2014.
Final assessment approved by City Council on December 30, 2015.
Streets included:
-
East side of NE 52nd Avenue from 85 feet north of NE Wygant Street to the south right-of-way line of NE Alberta Street
-
South side of NE Alberta Street from the east right-of-way line of NE 52nd Avenue to 265 feet west of NE 55th Avenue
Property owners are funding this project. If you have any questions about this project, please contact Local Improvement District Administrator and Project Manager Andrew Aebi at 503-823-5648 or via e-mail at andrew.aebi@portlandoregon.gov. If you have any questions about planned park improvements adjacent to the street, sidewalk and stormwater improvements, please contact Travis Ruybal of Portland Parks & Recreation at 503-823-5487 or go to this link: http://www.portlandoregon.gov/parks/article/423654