NE 47th Avenue Phase I LID

LID formed by City Council on April 6, 2016

Survey complete; 30% design complete; link to plans:      ftp://ftp02.portlandoregon.gov/PBOT/LID_Program/NE_47th_Avenue_LID/Plans/30%25/

60% plans scheduled for late March or early April 2017

90% plans scheduled for late May or early June 2017

100% plans scheduled for late July 2017

Advertise for bids Fall 2017

Utility relocation scheduled for early 2018

Construction scheduled for Spring and Summer 2018

Street includes:

  • NE 47th Avenue from north of NE Columbia Blvd. to NE Buffalo Street
  • NE 47th Avenue from NE Buffalo Street to NE Crystal Lane
  • NE 47th Avenue from NE Crystal Lane to south of NE Cornfoot Road
  • New temporary traffic signal at the intersection of NE Alderwood Road & Columbia Blvd. to accommodate construction detours (activated October 13, 2016)

Most funding for this project is being provided by Portland Bureau of Transportation System Development Charge (SDC) revenue.  Property owners including Portland Parks and Recreation and the Bureau of Environmental Services (BES) are providing LID funding for this project.  Additional non-LID is being provided by BES for a new dry line sanitary sewer, and from the Portland Water Bureau for replacement of a century-old cast iron water main.  If you have any questions about this project, please contact Local Improvement District Administrator and Project Manager Andrew Aebi at 503-823-5648 or via e-mail at andrew.aebi@portlandoregon.gov.