Schedule and Project Updates
St Johns Truck Strategy, Phase II
Construction Schedule
All dates (2019) are estimated and subject to change
Updated: August 1, 2019
Construction of the St. Johns Truck Strategy Phase II will be mostly complete by the end of September. The one element of the project that is delayed is the installation of the RRFB and HAWK signal. The plant that is manufacturing the steel poles for the project was shut down for several weeks last winter due to major flooding in Nebraska and, as a result, the signal poles will not be arriving on site until mid to late October.
LOCATION |
TYPE OF IMPROVEMENT |
ANTICIPATED START DATE (week of) |
ANTICIPATED END DATE (week of) |
N Lombard |
|||
N Weyerhaeuser to N Reno |
Sidewalk Infill |
Complete - awaiting final paving at curb ramps |
|
N Reno to N St. John |
Sidewalk infill |
Complete - awaiting final paving at curb ramps |
|
N Reno Intersection |
Curb extensions |
Complete - awaiting final paving at curb ramps |
|
N St John Ave intersection |
Intersection realignment |
Underway (Started week of April 1) |
Westside -- awaiting final paving at curb ramps Eastside -- sidewalks to be installed |
N Caitlin intersection |
Curb extensions |
July 15 |
Storm water facilities completed. |
|
Overall signing and restriping |
Underway |
End of November |
N St Louis- Fessenden |
|||
N Oswego |
Median refuge island and curb ramps |
Complete - awaiting final paving at curb ramps |
|
N Allegheny |
Median refuge island and curb ramps |
Complete - awaiting final paving at curb ramps |
|
N Tioga |
Median refuge island and curb ramps |
|
Complete - awaiting final paving at curb ramps |
N Smith |
Median refuge island and curb ramps |
|
Complete - awaiting final paving at curb ramps |
N Kellog |
Median refuge island and curb ramps |
|
Complete - awaiting final paving at curb ramps |
|
Rapid Flash Beacon |
End of October - Awaiting signal pole delivery |
End of October - Awaiting signal pole delivery |
N Seneca |
Median refuge island and curb ramps |
July 1 |
Complete - awaiting final paving at curb ramps |
|
Hawk Signal |
End of October - Awaiting signal pole delivery |
End of October - Awaiting signal pole delivery |
N Midway |
Curb extensions |
July 22 |
Complete - awaiting final paving at curb ramps |
|
Rapid flash beacon |
Aug 19 |
End of October - Awaiting signal pole delivery |
N Columbia Way |
Curb extensions |
August 12 |
End of November |
N Charleston |
Curb extensions, signal pole foundations |
July 15 |
End of November |
Signing and striping |
August |
End of November |
|
Speed humps |
End of August |
October |
|
N Columbia Way |
|||
Overall signing and striping |
August |
End of November |