Schedule and Project Updates

St Johns Truck Strategy, Phase II

Construction Schedule

All dates (2019) are estimated and subject to change

Updated: August 1, 2019

Construction of the St. Johns Truck Strategy Phase II will be mostly complete by the end of September. The one element of the project that is delayed is the installation of the RRFB and HAWK signal. The plant that is manufacturing the steel poles for the project was shut down for several weeks last winter due to major flooding in Nebraska and, as a result, the signal poles will not be arriving on site until mid to late October. 

 

 

LOCATION

 

TYPE

OF IMPROVEMENT

ANTICIPATED

START DATE

(week of)

ANTICIPATED

END DATE

(week of)

N Lombard

N Weyerhaeuser to N Reno

Sidewalk Infill

 

Complete - awaiting final paving at curb ramps

N Reno to N St. John

Sidewalk infill

 

Complete - awaiting final paving at curb ramps

N Reno Intersection

Curb extensions

 

Complete - awaiting final paving at curb ramps

N St John Ave intersection

Intersection realignment

Underway (Started week of April 1)

Westside -- awaiting final paving at curb ramps

Eastside -- sidewalks to be installed

N Caitlin intersection

Curb extensions

July 15

Storm water facilities completed.

 

Overall signing and restriping

Underway

End of November

N St Louis- Fessenden

N Oswego

Median refuge island and curb ramps

 

Complete - awaiting final paving at curb ramps

N Allegheny

Median refuge island and curb ramps

 

Complete - awaiting final paving at curb ramps

N Tioga

Median refuge island and curb ramps

 

Complete - awaiting final paving at curb ramps

 N Smith

Median refuge island and curb ramps

 

Complete - awaiting final paving at curb ramps

N Kellog

Median refuge island and curb ramps

 

Complete - awaiting final paving at curb ramps

 

Rapid Flash Beacon

End of October - Awaiting signal pole delivery

End of October - Awaiting signal pole delivery

N Seneca

Median refuge island and curb ramps

July 1

Complete - awaiting final paving at curb ramps

 

Hawk Signal

End of October - Awaiting signal pole delivery

End of October - Awaiting signal pole delivery

N Midway

Curb extensions

July 22

Complete - awaiting final paving at curb ramps

 

Rapid flash beacon

Aug 19

End of October - Awaiting signal pole delivery

 N Columbia Way

Curb extensions

August 12

 

End of November

N Charleston

Curb extensions, signal pole foundations

July 15

End of November

Signing and striping

August

End of November

Speed humps

End of August

October

N Columbia Way

Overall signing and striping

August

End of November