The Vision Zero Project List describes funded and unfunded safety fixes on the High Crash Network. Portland City Council adopted this list on July 13, 2017.

There are four categories of projects:

This list is for planning purposes only; projects may change. For more details, download the PDF or email Vision Zero.

High Crash Network street Project name*  Description and extent Status 

Proposed new or revised projects

92nd SE 92nd Ave Bikeway
Proposed new name: SE 92nd Ave Safety Improvements
Design and implement bicycle facilities between Holgate and Woodstock. Fill 1500' of sidewalk gaps between Stark and Clatsop. Upgrade or add crosswalks consisting of ADA ramps and curb extensions or islands in the 2- and 3-lanes sections. Unfunded
Capitol Outer Capitol Hwy Corridor Improvements Make safety improvements from Huber to Stephenson that include a road reorganization, curb extensions, medians, improved crossings, enhanced bike lanes, left turn pockets and improved signal timing. Partially funded

Columbia

Columbia Blvd Pedestrian Improvements Construct sidewalks and crossing improvements from Burr to Interstate 205. Project design will consider freight movement needs, consistent with policies, street classification(s) and uses. Unfunded 
Foster
Lents Town Center Improvements, Phase 2 Enhance bike facilities and implement Lents Town Center Business District Transportation Plan with new traffic signals, pedestrian amenities, wider sidewalks, pedestrian crossings, and street lighting from 94th to 101st. Unfunded
Outer Foster Rd Pedestrian Improvements Enhance bike facilities and construct sidewalks and crossing improvements to improve safety and access to transit from 102nd to Foster Place. Unfunded
Hawthorne Hawthorne Multimodal Safety Safety project to reduce sideswipe auto crashes and left turning auto crashes from 12th to 50th. Include safety improvements to reduce bike crashes and pedestrian crashes. Unfunded
Holgate Inner Holgate Bikeway
Proposed new name: Inner Holgate Bikeway & Pedestrian Improvements
Design and implement bicycle facilities and apply crosswalk spacing and lighting standards and design treatments for 20-25 mph MV speed from McCloughlin to Chavez. Project design will consider freight movement needs, consistent with policies, street classification(s) and uses. Unfunded
Killingsworth Outer Killingsworth Multimodal Safety Safety project to reduce rear end crashes and pedestrian crashes from Cully to Columbia (east leg). Upgrades to pedestrian crossings, including transit amenities, and bike facilities. Unfunded
NE Killingworth Safety Improvements Construct streetscape and multimodal safety improvements to increase opportunities to walk and enhance the main street character of this corridor from Martin Luther King Jr. Blvd. to 42nd Ave. Unfunded
Lombard
Lombard Multimodal Safety Safety project to reduce rear end and lane departure crashes from Interstate to Cully. Includes rebuild of Lombard/11th rail crossing to address crash history. Unfunded
N Lombard Corridor Improvements Design and implement multimodal safety and streetscape improvements to improve safety and promote pedestrian-oriented uses from Woolsey to Interstate and to create a safe, pleasant pedestrian link over I-5, including intersections improvements at Montana & Lombard. Unfunded
Marine Marine Drive Auto & Pedestrian Safety Safety project to reduce run off road crashes and enhance pedestrian crossings from 4,400 feet west of Portland Rd. to 1,100 feet east of 13th Ave. Unfunded
Marine & Lombard (continguous segment) N Marine/Lombard Multimodal Safety Safety project to reduce lane departure crashes and enhance pedestrian and bike crossings from 4,400 feet west of Portland Rd. to the intersection of Lombard & Columbia. Unfunded
MLK Grand/MLK ITS
Proposed new name: Grand/MLK ITS & Multimodal Safety
Install bike and ped crossing improvements and ITS infrastructure (communication network, enhanced bus detection, Bluetooth detection, CCTV cameras, and vehicle /pedestrian detectors) from Columbia to Hawthorne. These ITS devices allow us to provide more efficient and safe operation of our traffic signal system consistent with our policies of moving people more effectively. Partially funded
Powell Inner Powell Blvd Corridor Improvements Retrofit existing street with multimodal safety improvements from Ross Island Bridge to Interstate 205 including enhanced pedestrian and bicycle crossings, pedestrian and bike activated signals, median islands with trees, redesign of selected intersections and stormwater management facilities. Unfunded
Sandy Sandy Blvd Corridor Improvements, Phase 2 Construct multimodal improvements from Burnside to I-205 including elements such as transit priority, bicycle facilities, improved pedestrian crossings, streetscape improvements including lighting, and safety improvements. Unfunded
Outer Sandy Blvd Corridor Improvements Construct multimodal safety improvements from 99th to 122nd. Widen street to three lanes with a sidewalk and bike lanes from 141st to 165th. Project design will consider freight movement needs, consistent with policies, street classification(s) and uses. Unfunded

Low-cost unfunded projects

102nd 102nd Ave Pedestrian Safety Apply crosswalk spacing and lighting standards and design treatments for 20-25 mph MV speed from Halsey to Burnside, implement intersection safety treatments at Glisan. Unfunded
Division Middle Division Multimodal Safety Apply crosswalk spacing and lighting standards from 44th to 60th and implement intersection safety treatments at 50th. Unfunded
Foster Foster Rural Road Safety Safety project to improve roadside safety on Outer Foster from Foster Place to Jenne Rd (city limit), including pedestrian/transit enhancements. Unfunded
Fremont Fremont Multimodal Safety Apply crosswalk spacing and lighting standards and design treatments for 20-25 mph MV speed from Missouri to 141st. Unfunded
Glisan Inner Glisan Multimodal Safety Apply crosswalk spacing and lighting standards and design treatments for 20-25 mph MV speed from Sandy to 82nd and enhance bike facilities. Unfunded
Interstate Interstate Bike Safety Enhance existing bike facilities with green paint, limited parking removal, buffer and delineation in select locations from Oregon to Columbia. Unfunded
Killingsworth North Killingsworth Multimodal Safety Apply crosswalk spacing and lighting standards and design treatments for 20-25 mph MV speed from Willamette to Interstate. Unfunded
Stark Inner Stark Multimodal Safety Apply crosswalk spacing and lighting standards and design treatments for 20-25 mph MV speed from 28th to 62nd. Unfunded

Other TSP safety projects

102nd NE 102nd Ave Corridor Improvements Construct sidewalks and improved crossings, install bicycle facilities, and make traffic safety improvements from Sandy to Weidler. Partially funded
122nd 122nd Ave Corridor Improvements Design and implement multimodal improvements to sidewalks, crossings, bicycle facilities, transit stops, striping, and signals to enhance ped/bike safety, access to transit, and transit operations from Sandy to Foster. Project design will consider freight movement needs, consistent with policies, street classification(s) and uses. Partially funded
4th
SW 4th Ave Corridor Improvements Improves the street environment on SW 4th Avenue adjacent to Portland State University from Lincoln to Columbia by adding bicycle facilities, curb bulb-outs, enhanced pedestrian crossings, traffic signals, and green street features. As part of the project, reconfigure 4th Ave fr Unfunded
SW/NW 4th Ave Bikeway Design and implement a protected bikeway on 4th Ave from Madison to Flanders to provide a bikeway couplet with Broadway connecting PSU, Downtown, and Old Town / Chinatown. Unfunded
7th Central Eastside 7th Ave Corridor Improvements Design and implement a bikeway from I-84 to Division, connecting to Sullivan's Crossing ped/bike bridge, with separated bikeway segments, neighborhood greenway segments, pedestrian improvements, and crossing improvements as needed. Includes enhancement o Unfunded
82nd 82nd Ave Corridor Improvements Design and implement multimodal improvements to sidewalks, crossings, transit stops, striping, and signals to enhance ped/bike safety, access to transit, and transit operations from 82nd to Clatstop. Project design will consider freight movement needs, consistent with policies. Unfunded
Barbur Inner Barbur Corridor Improvements Construct Improvements for transit, bikes and pedestrians from Broadway to Terwilliger. Transit improvements include preferential signals, pullouts, shelters, left turn lanes and sidewalks. Unfunded
Outer Barbur Corridor Improvements Complete boulevard design improvements from Terwilliger to 65th including sidewalks and street trees, safe pedestrian crossings, enhance transit access and stop locations, traffic signal at Barbur/30th, and bike lanes (Bertha - City Limits). Unfunded
West Portland Town Center Pedestrian Improvements Improve sidewalks, lighting, crossings, bus shelters, and benches on Barbur from Huber to Markham ES, Capitol Hwy, and surrounding neighborhood streets. Unfunded
Beaverton-Hillsdale Beaverton-Hillsdale Hwy Corridor Improvements Build new sidewalks, improve crossings, and enhance access to transit from Capitol to city limit. Project design will consider freight movement needs, consistent with policies, street classification(s) and uses. Partially funded
B-H Hwy/Bertha/Capitol Hwy Improvements Redesign intersection to improve safety at Beaverton-Hillsdale Highway, Bertha Blvd. and Capitol Hwy. Unfunded
Broadway Post Office Blocks Improvements, Phase 1 Extend Johnson St as an east-west multimodal street through the Post Office Blocks redevelopment site, including diverter at 9th Ave. Extend Park Ave north to Johnson. Add traffic signals at 9th/Everett and 9th/Glisan. Create pedestrian connections throu Unfunded
Post Office Blocks Improvements, Phase 2 Extend the Green Loop through the Broadway Corridor redevelopment site from North Park Blocks to Broadway Bridge. Enhance existing bike lanes along Broadway and Lovejoy viaducts. Unfunded
NE Broadway Corridor Improvements, Phase 1 Enhance existing bike lanes and improve pedestrian/bicycle crossings from Broadway Bridge to NE 24th. Add traffic signals, improve signal timing, improve transit stops, and construct streetscape improvements. Unfunded
NE Broadway Corridor Improvements, Phase 2 Design and implement bicycle facilities and improve pedestrian/bicycle crossings from NE 24th to 42nd. Construct traffic signals, improve transit stops, and construct streetscape improvements. Unfunded
Broadway Multimodal Streetscape Improvements Enhance the existing bikeway on Broadway from Hoyt to Clay. Includes the construction of a protected bikeway, signal improvements, short-term parking and loading zones, and shorter pedestrian crossings. Consider a protected intersection at Broadway/Burnside and a northbound Unfunded
SW Broadway Bikeway and Streetscape Improvements Enhances the existing protected bikeway and sidewalks on SW Broadway adjacent to Portland State University from Clay to Jackson. Includes the construction of a raised bikeway, sidewalk amenities, green street features, ADA improvements, pedestrian islands, and curb bulb-outs. Unfunded
Burnside Burnside Bridge Rehabilitation, Phase 1 Rehabilitate mechanical system, approach structure, corrosion control, phase 1 seismic. Unfunded
Outer W Burnside Corridor Improvements Widen street from Vista to Skyline to add bicycle facilities, improve sidewalks, lighting, crossings and provide traffic signals and turn lanes at Burnside & Skyline. Partially funded
Inner E Burnside Ped/Bike Improvements Design and implement bicycle facilities and improve pedestrian crossings to provide access to schools and transit from 30th to 82nd. Unfunded
Inner Burnside Multimodal Improvements Reconfigure lanes from SW Park Ave to SE 12th Ave to reduce transit delay and improve pedestrian and bicycle safety. Enhance existing bike lanes across the bridge to provide climbing lanes and more physical separation from traffic. Extend bike lanes west Unfunded
W Burnside/Couch Corridor Improvements, Phase 1 Construct transportation improvements from 16th to Naito including traffic signals, turn lanes, curb extensions, bicycle network improvements, crossing improvements, and improvements for transit operations. Unfunded
W Burnside/Couch Corridor Improvements, Phase 2 Implements a one-couplet design from 2nd to Naito including new traffic signals, widened sidewalks, curb extensions, bike lanes, on-street parking and street trees. This project will be coordinated with ODOT to address potential impacts to the I-405 interchanges, overcrossings and ramps. Unfunded
W Burnside Corridor Improvements Design and construct boulevard improvements from 15th to Vista including pavement reconstruction, wider sidewalks, curb extensions, safer crossings, new traffic signals, and traffic management. Unfunded
Capitol Capitol Hwy Corridor Improvements Improve SW Capitol Highway from SW Multnomah Boulevard to SW Taylors Ferry Road to include a continuous sidewalk(s), safe crossings and bicycle access along the corridor. Partially funded
B-H Hwy / Bertha / Capitol Hwy Improvements Redesign intersection to improve safety at Beaverton-Hillsdale Highway, Bertha Blvd. and Capitol Hwy. Unfunded
Capitol/Vermont/30th Intersection Improvements Realign the Capitol/Vermont/30th intersection and provide sidewalks, bike lanes, and drainage improvements. Unfunded
Inner Capitol Hwy Corridor Improvements Barbur to Sunset Blvd.: Construct sidewalks, crossing improvements for access to transit, and bike improvements, and install left turn lane at the Capitol/Burlingame intersection. Unfunded
West Portland Town Center Pedestrian Improvements Improve sidewalks, lighting, crossings, bus shelters, and benches on Barbur, Capitol Hwy from Huber to Markham ES, and surrounding neighborhood streets. Unfunded
Chávez César Chávez Corridor Improvements NE Broadway to Woodstock: Repair street, upgrade sidewalks, and add pedestrian/bicycle crossing improvements. Upgrade signals and make striping changes to improve traffic safety and transit operations. Unfunded
Columbia Columbia Blvd Protected Bikeway Design and implement a protected bikeway or multi-use path from Lombard to MLK. Project design will consider freight movement needs, consistent with policies, street classification(s) and uses. Unfunded
Division Outer Division Corridor Improvements Construct streetscape improvements to enhance sidewalks, lighting, crossings, bus shelters and benches, and bicycle facilties from I-205 to the city limit. Partially funded
Inner Division Corridor Improvements, Phase 2 Design and implement streetscape improvements to enhance sidewalks, lighting, crossings, access to transit, transit stops, and signals from Chávez to 60th. Add separated in-roadway bicycle facilities (52nd - 60th). Unfunded
Inner Division Corridor Improvements, Phase 3 Construct improvements that enhance access to transit, improve safety and enhance the streetscape such as traffic signals, lighting, bus shelters, benches, and crossings from 60th to 82nd. Unfunded
Fremont NE Fremont Streetscape Improvements Design and implement streetscape improvements from 42nd to 52nd to enhance sidewalks, lighting, crossings, transit stops, and signals. Unfunded
Parkrose Neighborhood Greenway Design and implement a neighborhood greenway. Project includes a multi-use path and bridge from I-205 Path to NE Fremont St and sidepath along the south side of NE Fremont St. from 102nd to 112th. Unfunded
Glisan Outer Glisan Safety and Streetscape Improvements 122nd to 162nd: Install bicycle facilities on existing street. Install street trees (requires sidewalk widening, curb extensions, and/or bioswales). Install a signal at 131st Pl to improve pedestrian and vehicular access to Glisan St. Partially funded
60th Ave MAX Station Area Improvements Implement pedestrian and bicycle improvements in the 60th Ave MAX Station Area identified in the Eastside MAX Station Area Communities Project. Unfunded
Gateway--Glisan Streetscape Improvements Implement Gateway regional center plan with boulevard design retrofit, new traffic signals, bike facilities, improved pedestrian facilities and crossings, and street lighting from I-205 to 106th. Unfunded
I-205 Multi-use Path Crossings Improve crossings and access to I-205 multi-use path at Glisan, Stark/Washington, and other intersections as needed. Unfunded
Inner Glisan Bikeway Design and implement bicycle facilities from 47th to I-205. Unfunded
Halsey 60th Ave MAX Station Area Improvements Implement pedestrian and bicycle improvements in the 60th Ave MAX Station Area identified in the Eastside MAX Station Area Communities Project. Unfunded
Halsey St Bikeway, Phase 1 Implement a lane reorganization including bicycle facilities from 67th to 80th, and add improved pedestrian/bicycle crossings at 67th and 80th. Unfunded
Halsey St Bikeway, Phase 2 Design and implement bicycle facilities and improved crossings from 80th to 99th. Unfunded
Outer Halsey Pedestrian Improvements Construct sidewalks, crossing improvements for pedestrian travel, and access to transit improvements from 122nd to 162nd. Unfunded
Hawthorne Inner Hawthorne Multimodal Corridor Improvements Signalize the top of the ramp from SW Naito to Hawthorne Bridge to improve safety and capacity for all modes. Construct an eastbound protected bikeway with transit islands to improve pedestrian and bicycle safety and comfort as well as transit operations. Unfunded
Holgate Holgate Blvd Corridor Improvements Reconstruct pavement structure and stormwater drainage facilities, improve corner curb ramps to ADA standards, improve pedestrian crossings, and add bicycle facilities from Chávez to 52nd. Unfunded
Outer Holgate Ped/Bike Improvements Construct sidewalks and crossing improvements to facilitate pedestrian travel and access to transit from I-205 to 140th. Extend bicycle facilities from 130th to 136th. Unfunded
Lombard St Johns Truck Strategy, Phase 2 Address pedestrian safety, bicycle safety and neighborhood livability impacts associated with cut-through truck traffic on N St Louis Ave and N Fessenden St. Construct pedestrian crossing safety and traffic calming improvements, such as curb extensions and median islands, and redesign the Columbia/Portland intersection as outlined in the St Johns Truck Strategy Phase II. Partially funded
Lombard St ITS Communications infrastructure from Philadelphia to MLK including closed circuit TV camera, Bluetooth detection, improved bus priority variable message signs for remote monitoring and control of traffic flow at the intersections with MLK Jr, Interstate, Greeley, Portsmouth, Philadelphia/Ivanhoe. Unfunded
N Lombard Main Street Improvements Implement main street improvements along N Lombard from Tyler to Woolsey consistent with the St Johns/Lombard Plan, including curb extensions and street lighting. Provide separated in-roadway bicycle facilities from Ida to Portsmouth. Unfunded
Powell Outer Powell Blvd Corridor Improvements, Phase 1 Widen street to three lanes (inclusive of a center turn lane) with sidewalks and buffered bike lanes or other enhanced bike facility from 116th to 136th. Add enhanced pedestrian and bike crossings. Partially funded
Outer Powell Blvd Corridor Improvements, Phase 2 Widen street to three lanes (inclusive of a center turn lane), or four lanes from 162nd – 174th if specific traffic conditions are met, with sidewalks and buffered bike lanes or other enhanced bike facility. Add enhanced pedestrian and bike crossings from 99th to 116th. Partially funded
Inner Powell Bikeway Design and implement bicycle facilities from 71st Ave. to Interstate 205. Project design will consider freight movement needs, consistent with policies, street classification(s) and uses. Unfunded
East Portland Access to Employment This project will build sidewalks and crossing improvements on Powell Blvd, improve sidewalks for access to transit, improve transit stops, improve transit operations, and build the 100s and 150s Neighborhood Greenways. Unfunded
Sandy Hollywood Town Center Safety Improvements Implement multimodal safety improvements from 37th to 47th including traffic signals, restriping, improved pedestrian crossings, and connections to transit center. Unfunded
Inner Sandy Blvd Bikeway Design and implement separated in-roadway or protected bicycle facilities from Burnside to 47th. Project design will consider freight movement needs, consistent with policies, street classification(s) and uses. Unfunded
Sandy Blvd ITS Install ITS infrastructure (communication network, enhanced bus detection, Bluetooth detection, CCTV cameras, and vehicle /pedestrian detectors) from 14th to 82nd. These ITS devices allow us to provide more efficient and safe operation of our traffic signal system consistent with our policies of moving people more effectively. Unfunded
Stark Gateway--Stark/Washington Streetscape Improvements Implement Gateway regional center plan with boulevard design retrofit including new traffic signals, improved pedestrian facilities and crossings, and street lighting from 92nd to 111th. Project design will consider freight movement needs, consistent with policies, street classification(s) and uses. Unfunded
I-205 Multi-use Path Crossings Improve crossings and access to I-205 multi-use path at Glisan, Stark/Washington, and other intersections as needed. Unfunded
Outer Stark Ped/Bike Improvements Construct sidewalks and crossing improvements and provide bicycle facilities from 108th to 162nd. Project design will consider freight movement needs, consistent with policies, street classification(s) and uses. Unfunded
SE Washington Bikeway Gap Design and implement bicycle facilities from 76th to 92nd. Project design will consider freight movement needs, consistent with policies, street classification(s) and uses. Unfunded
Thorburn / Gilham Safety Improvements Design and implement a pedestrian walkway, improved crossings, and traffic calming elements from Burnside to Stark. Unfunded
Terwilliger Terwilliger Bikeway Gaps Design and implement bicycle facilities to fill in gaps in the Terwilliger Bikeway at 5 locations between Sheridan and Boones Ferry. Unfunded

Funded projects

102nd 102nd Ave Multimodal Safety Sidewalk and road reorganization from Sandy to Halsey. Funded
122nd 122nd Ave Multimodal Safety Continue with safety improvements to 122nd Corridor from Marine Drive to Flavel St. and partnership with TriMet to increase bus service.  Funded
4th SW 4th Ave Paving & ADA Accessibility Paving and ADA upgrades from Lincoln to Burnside through FOS, and potential multimodal safety upgrades through Central City in Motion. Funded
Barbur Barbur Demonstration Project Crossings and sidewalk infill from SW 19th Ave. to Spring Garden. Funded
Beaverton-Hillsdale Beaverton-HIllsdale Hwy Multimodal Safety & Paving Paving from 21st to 45th, protected biking and walking paths from 30th to 39th, new crossing with RFBs and median with trees at 35th, crosswalk on west leg of signal at 30th. Funded
Burnside W Burnside Safety Improvements Sidewalk infill from 24th to Uptown Terrace, crossing improvements at 20th Place and at I-405, intersection rebuild at 18th/19th. Funded
Capitol Capitol Hwy Multimodal Safety & Stormwater 37th to Barbur: sidewalk, bike lanes, pedestrian crossings, stormwater facilities Funded
Outer Capitol Hwy/49th Multimodal Safety Road reorganization from Huber to 49th & Hidalgo. Funded
Division Outer Division Multimodal Safety Speed safety cameras, speed reader boards, speed limit reduction to 30 mph, safer signal timing, sidewalk infill, additional lighting, more rapid flashing beacons and pedestrian hybrid beacons, protected bike lanes, safety education & outreach, raised center median, and shorter crossing distances at crosswalks from 82nd to city limit. Funded
Foster Foster Transportation & Streetscape 50th to 90th: buffered bike lanes, street trees, bus shelters. 82nd-90th: paving. 84th-88th: sidewalk widening. Holgate-67th, 84th-89th: street lights. Crossing improvemetns at 50th, 65th, 69th, 70th, 75th, 84th, Cora. Curb extensions, corner redesigns, signal modifications. Funded
Foster Road Corridor Improvements Improve sidewalks, lighting, crossings, bus shelters, and benches on Foster from 50th to Woodstock and improve pedestrian crossings to benefit access to transit. Install separated in-roadway bicycle facilities and widen substandard sidewalks from 50th to 90th. Funded
Glisan Outer Glisan Multimodal Safety Road reorganization from 82nd to 162nd (city limit) to support crossing improvements. Funded
Halsey Halsey/Weidler Streetscape Improvements Implement Gateway Regional Center Plan boulevard design including new traffic signals, improved pedestrian facilities and crossings and street lighting from I-205 to 114th. Funded
Killingsworth Killingsworth Pedestrian Improvements Sidewalk infill from 42nd to Lombard. Funded
Lombard Lombard/Burgard Rd Safety & Freight Improvements Multiuse path and freight improvements from Columbia to St. Johns Ave. Funded
Lombard Safety Extension Road reconfiguration, signal upgrades, RFB at Drummond, and ADA improvements from Fiske to Wilbur. Funded
Marine
Marine Drive Multimodal Safety Speed safety cameras, new traffic signal at 122nd, fill gaps in the multi-use path, rapid flashing beacons at 112th, rapid flashing beacons at 138th, buffered bike lanes with bike modified rumble strips in the buffer area from 112th to 122nd, shoulder rumble strips from 33rd-185th, centerline rumble stripsfrom  4,000’ east of NE 33rd to 185th. Funded
Marine Drive Trail Gaps Close gaps in Marine Dr Trail from 112th to 122nd. Funded
MLK MLK Pedestrian Safety Signage, striping, lighting, tree visibility, and other safety improvements from Ainsworth to Cook (Ainsworth, Russell, Jarret, Simpson, Jessup, Church, Emerson, Sumner, Alberta, Wygant, Going, Mason, Cook, Failing, Beech, & Graham). Funded
Powell Inner Powell Crosswalk Safety Crossing and ADA improvements from 21st to 82nd (21st, 24th, 26th, 28th, 31st, 33rd, 34th, 36th, Chavez, 47th/48th, 57th/58th, 61st, 71st/72nd, 79th/80th, and 82nd). Funded
Middle Powell Multimodal Safety Crosswalks, sidewalks, bike facilities, center turn auto lane, lighting, and RFBs from 112th to 136th. Funded
Sandy Sandy Crossing Improvements Crossing improvements from 79th to Killingsworth. Funded
Stark Jade & Montavilla Connected Centers Add protected bike lane on SE Washington from 72nd to 92nd Ave/ I-205 multi-use path. Preferably reconfigure left turn movements from 82nd to the Stark/Washington couplet to reduce neighborhood cut-through traffic impacts on local streets, particularly SE Alder. Alternatively, construct sidewalk, lighting, curb and drainage on SE Alder from 82nd to 84th Ave where cut-through traffic is problematic currently. Enhanced crossings of arterials, including SE Washington and Stark at 84th and 86th.  Funded

*Project name is used for reference only, and is not necessarily a formal name.