Roselawn Bundle Water Main Replacement


Sign Up for Project Updates

Join the project email newsletter to get timely updates delivered directly to your inbox. Click on the link and select the checkbox next to "Roselawn Bundle Water Main Replacement" to sign up.

Over a half mile—4,001 feet—of water main pipe in the Cully Neighborhood will be replaced with more seismically resilient pipe. Five hydrants will be installed and 91 service connections will be renewed.

Water main installation involves cutting the road surface the length and width of the pipe trench, excavating the trench, replacing old pipe or installing new pipe, filling the trench, and restoring the road surface.

Why

Since 2010 there have been more than 10 breaks and leaks along this pipe, brought on by the poor condition of the pipe.

When

Construction begins mid- to late- August

Where

  • NE 48th Ave. from Killingsworth to Roselawn
  • NE 49th Ave. from Alberta to Killingsworth
  • NE Roselawn St. running east of 49th for 140 feet
  • NE Sumner St. running east of 49th for 30 feet
  • NE Sumner St. from 57th to 60th
  • NE Roselawn St. from 62nd to Cully

Preconstruction Activities

  • Soon, survey crews will mark right-of-way boundaries, utility vaults, and other landmarks.
  • Utilities will use paint or colored flags to mark their underground lines.

Project Schedule

Construction begins in August and is expected to be completed by the end of December.

Contact

Sign up for project email updates at portlandoregon.gov/water/emailnews. Select the “Roselawn” option.

Questions? Katy Asher, 503-865-6054, or Katy.Asher@portlandoregon.gov.