On this pageMeetings | Oct. 3 Meeting | Oct. 10 Meeting


photo of Site Advisory Group meeting

Portland is building a new filtration facility to remove the microorganism Cryptosporidium and other potential contaminants, and to help inform this seven-year project, the Bull Run Filtration Site Advisory Group meets monthly to discuss details and opportunities for the Bull Run Filtration Project. 

The group will help project staff develop a Good Neighbor Agreement by providing an independent community perspective on the facility design, construction, and ongoing operation. Group members include adjacent property owners to future filtration facility site in rural Multnomah County, farm operators, local school representatives, area water utilities, the environmental community, and others.

Next Event

November 8, 2019: City of Wilsonville’s Willamette River Water Treatment Plant Tours

Space is limited and RSVPs are required. See details below.

 

Meetings

   
October 3, 2019 Site Advisory Group Orientation - Part 1
October 10, 2019 Site Advisory Group Orientation - Part 2
November 2019 Water Treatment Plant Tour
December 2019 Break
January 2020 Design Phase - Part 1
February 2020 Water Treatment Plant Tour
March 2020 Design Phase - Part 2
April 2020 Design Phase - Part 3
May 2020 Design Phase - Part 4
June 2020 Community Open House
July 2020 Construction Phase - Part 1
August 2020 Construction Phase - Part 2
September 2020 Operations Phase - Part 1
October 2020 Operations Phase - Part 2
November 2020 Draft Good Neighbor Agreement
December 2020  Break
January 2021 Community Open House
Final Good Neighbor Agreement

Oct. 3, 2019 Site Advisory Group meeting

 Video of the Oct. 3, 2019, Site Advisory Group Meeting

OCT. 3 MEETING RESOURCES

1. Agenda

2. Site Selection Report

Six potential sites for the filtration plant were evaluated in 2017-18:

  • City-owned property adjacent to Carpenter Lane
  • Lusted Hill (with expansion)
  • Headworks
  • Larson’s Ranch
  • Powell Butte
  • Roslyn Lake

Carpenter Lane was selected for the new filtration plant site because it was the only property that met all facility siting criteria, including maximizing gravity flow, being close to existing and future pipelines, site size, site slopes, and geologic conditions, being already owned by the City of Portland, and ability to meet the compliance schedule. The Portland Water Bureau purchased the Carpenter Lane site in the 1970s to use for future water system facilities. The analysis can be found in the Bull Run Filtration Project Preferred Alternatives Report.

3. Advisory Groups and Good Neighbor Examples

At the Oct. 3 meeting, the Bull Run Filtration project Site Advisory Group requested examples of community advisory groups and Good Neighbor Agreements. A few examples are below, noting the process and outcomes will be much more robust with the larger project scope for the filtration facility.

 

4. Feedback

Do you have questions or comments about this meeting or the Bull Run Treatment Projects? Submit your feedback through our project comment form or contact us at bullrunprojects@portlandoregon.gov or 503-865-6039.

Go to the top of page


Oct. 10, 2019 Site Advisory Group meeting

 

Video of the October 10, 2019 Site Advisory Group Meeting

OCT. 10 MEETING RESOURCES

1. Agenda

2. PowerPoint Presentation 

3. Topic Input Handout

4. November Willamette River Water Treatment Plant 

The Portland Water Bureau is hosting two opportunities to tour the City of Wilsonville’s Willamette River Water Treatment Plant with Site Advisory Group members. Attendees will see the equipment and processes at work at a drinking water filtration facility. Join us on a tour:

Date: November 8, 2019
Time Options:
10 a.m. – noon (lunch provided)
2 p.m. – 4 p.m. (snack provided)
Location: Wilsonville Willamette River Water Treatment Plant
10350 SW Arrowhead Creek Lane, Wilsonville, OR 97070

Space is limited and RSVPs are required. Additional tour details will be provided to confirmed tour participants. Visit www.surveymonkey.com/r/PWBWilsonville by Nov. 4 to sign up

5. Join the Site Advisory Group

The current Bull Run Filtration Site Advisory Group members include adjacent property owners of the future filtration facility site as well as local representatives from Surface Nursery, Sandy River Watershed Council, Johnson Creek Watershed Council, East Multnomah County Soil and Water Conservation District, City of Sandy, and a recent graduate of the Oregon Trail Academy. Now is your opportunity to request a seat at the table. 

Membership requires a commitment to participate in monthly work sessions. Regular meetings are currently scheduled through October 2020 to take place 6-8 p.m., the second Thursday of each month (excluding November and December 2019 and June 2020). Anyone interested in joining should submit their contact information and brief a description of interest by Nov. 30, 2019 at  www.surveymonkey.com/r/AdvisoryMember. The current Site Advisory Group members will review and make a decision on additional members for at-large positions in December 2019.

Can't commit? You don't need to be a member to provide valuable input on Advisory group topics. Site Advisory Group meetings are open to the public and include opportunities for public input. Meetings are also recorded and videos will be available online with additional opportunities to give feedback or ask questions. 

6. Feedback

Do you have questions or comments about this meeting or the Bull Run Treatment Projects? Submit your feedback through our project comment form or contact us at bullrunprojects@portlandoregon.gov or 503-865-6039.