Appeal 14011
Appeal Summary
Status: Decision Rendered - Held over from 9/21/16 for additional staff review
Appeal ID: 14011
Submission Date: 9/19/16 12:52 PM
Hearing Date: 9/28/16
Case #: B-002
Appeal Type: Building
Project Type: commercial
Building/Business Name:
Appeal Involves: Addition to an existing structure
Proposed use: Access to (E) catwalk T4 berth 411
Appeal Information Sheet
Appeal item 1
| Code Section | OSSC Section 1803.5.12 |
|---|---|
| Requires | OSSC Section 1803.5.12 consequences of liquefaction due to differential settlement, soil strength loss due to lateral soil movement and lateral soil loads on foundations based on site peak ground acceleration for the maximum considered earthquake ground motions. |
| Code Modification or Alternate Requested | |
| Proposed Design | The project scope includes the design of a New Access Ramp/Walkway at the T-4 Wharf - Berth 411 located at 11040 N Lombard St in Portland, Oregon. The structure consist of (1) Steel framed upper landing on the shore, (1) Steel frame lower landing suspended from the Berth 411 structure above, (1) steel framed access ramp connecting the upper and lower landings and (1) additional steel framed walkway connecting the lower level landing to the existing Fire System Maintenance Walkway beneath the dock at the lower level. The upper landing is founded on shallow foundations using a bearing pressure of 2500 psf under static loading in accordance with the recommendations of the geotechnical report. In accordance with section 1803 of the OSSC Geo Engineers has conducted a geotechnical investigation and prepared a site specific seismic hazard geotechnical report dated June 10. The report states that the design of the project is feasible for static conditions, but may not be practical to design the ramp and platform for seismic conditions. Under seismic loads, liquefaction induced settlements of about 4 to 5 inches with a corresponding lateral spread of about 24 inches may be expected at the location of the proposed ramp abutment, located 35 feet back from the top of the river bank. The geotechnical report shows the river bank on which the foundations for the upper landing are located has a static slope stability factor of safety (FS) is 1.5 and seismic FS of 0.8. This implies that under Maximum Considered Earthquake, failure of the riverbank is likely. Per OSSC the required FS under seismic conditions is 1.1. It is not practical and cost prohibitive to design for the anticipated slope failure during a Maximum Considered Earthquake. The structure has not been designed to accommodate expected movements during a Maximum Considered Earthquake. Instead, the structure has been designed to allow limited rotation to accommodate some vertical movement between the upper level foundation and the lower level support beneath the pier. In addition, PTFE slide bearings have been provided at the top foundation to allow horizontal movement in line with the ramp. This will allow for some soil settlement over time and adequate performance during smaller seismic events. In case of a Maximum Considered Earthquake, in the event of the river bank failure, it is likely that the upper landing will lose support, and these movements would most likely overcome the ability of the walkway's structural system to adjust to movement. |
| Reason for alternative | The purpose of the new access ramp is to provide OSHA compliant access to the existing maintenance walkway beneath the pier at Berth 411. We are attempting to provide safe access for the limited times maintenance staff are required to work from the existing catwalk. In addition, there is an existing pathway to access the shore and stair up to the wharf at the far end that will remain. This provides an alternate means of egress in the improbable likelihood someone is using the under dock catwalk during a design seismic event. Engineering will also be provided to show that the Berth 411 structure will not be impacted should the access ramp lose it's foundation support at the upper landing due lateral spreading. As noted above, we have designed an at-grade foundation at the upper landing of our proposed ramp to allow for some soil settlement over time and adequate performance during smaller seismic |
Appeal Decision
Access Ramp/Walkway, not accessible by the public and with limited occupancy and use, to be constructed without mitigating MCE induced liquefaction displacements: Granted as proposed.
The Administrative Appeal Board finds that the information submitted by the appellant demonstrates that the approved modifications or alternate methods are consistent with the intent of the code; do not lessen health, safety, accessibility, life, fire safety or structural requirements; and that special conditions unique to this project make strict application of those code sections impractical.
Pursuant to City Code Chapter 24.10, you may appeal this decision to the Building Code Board of Appeal within 180 calendar days of the date this decision is published. For information on the appeals process and costs, including forms, appeal fee, payment methods and fee waivers, go to www.portlandoregon.gov/bds/appealsinfo, call (503) 823-7300 or come in to the Development Services Center.