Appeal 33632
Appeal Summary
Status: Decision Rendered
Appeal ID: 33632
Submission Date: 12/30/24 10:28 AM
Hearing Date: 1/8/25
Case #: P-002
Appeal Type: Plumbing
Project Type: commercial
Building/Business Name: Portland Art Museum
Appeal Involves: Erection of a new structure,Alteration of an existing structure
Proposed use: Museum
Project Address: 1219 SW Park Ave
Appellant Name: Joshua Stein
LUR or Permit Application #: Permit 19-258855-CO
Stories: 5 Occupancy: -1, A-2, A-3, B, S-1, M Construction Type: I-B
Fire Sprinklers: Yes - Throughout per NFPA-13
Plans Examiner/Inspector: Kathy Aulwes
Plan Submitted Option: pdf [File 1] [File 2] [File 3] [File 4]
Payment Option: electronic
Appeal Information Sheet
Appeal item 1
| Code Section | 2017 OPSC 1101.12 |
|---|---|
| Requires | §1101.12.1: The location and sizing of drains and gutters shall be coordinated with the structural design and pitch of the roof. |
| Code Modification or Alternate Requested | This appeal is to allow for the removal of an existing through-wall secondary overflow scupper drain blocked by a new building addition. The existing affected roof has adequate structural strength to support ponding water to a height where it will overflow into adjacent roof portions to drain; a new electronic water alarm tied into the building automation system (BAS) will allow early warning of ponding water to building personnel. |
| Proposed Design |
|
| Reason for alternative | The new Rothko Pavilion addition will be built directly adjacent to the Portland Art Museum’s 1931 Ayer Wing of the Main Building, which will require an existing secondary through-wall overflow roof scupper to be removed to prevent the overflow water from entering the new Rothko Pavilion interior. A new secondary overflow drain cannot be installed into this roof without significantly impacting the historic interior of the Ayer Wing. An alternate was studied to install a new secondary overflow drain through the exterior parapet of the Ayer Wing and into the Rothko Pavilion, but no feasible path or connection point was found. A proposed electronic water alarm installed within 6-inches of the existing primary roof drain would allow for its installation on an adjacent exterior parapet wall above the primary roof drain. If ponding water were to reach the water alarm, a signal would be sent to the museum’s building automation system to alert personnel of an issue. This alarm would provide an earlier indication of a potential ponding issue than the original through-wall scupper installed at approx. 11-inches above the primary roof drain. If the alarm were to fail or if personnel could not reach the roof area in adequate time, the ponding water would overflow into adjacent roof areas and on to their respective primary/secondary roof drains. Supplemental calculations show that the existing roof structure for the area in question can adequately support this ponded water as it flows into adjacent roof areas. Roof elevations and slopes used in the structural calculations are based on original as-built drawings and have been verified in the field. 2017 OPSC §1101.12 requires the location of roof drains to be coordinated with the building’s structural design. Secondary roof drains shall not allow ponding of water to exceed that for which the roof was designed. The proposed design will allow for an early warning to building personnel via the museum’s building automation system for corrective action. The existing building’s roof has adequate capacity to allow ponding water to overflow into adjacent roof portions where it can drain. CONCLUSION: Relevant Attachments:
|
Appeal Decision
Granted provided the roof structure is confirmed during plan review to be structurally sufficient for the additional water retention.
" ""The Administrative Appeal Board finds with the conditions noted, that the information submitted by the appellant demonstrates that the approved modifications or alternate methods are consistent with the intent of the code; do not lessen the health, safety, accessibility, life, fire safety or structural requirements; and that special conditions unique to this project make strict application of those code sections impractical.
Under City Code Chapter 24.10, you may appeal this decision to the Building Code Board of Appeal within 90 calendar days of the date this decision is published. For information on the appeals process, how to file a reconsideration, and how to appeal to the Building Code Board of Appeal, go to https://www.portland.gov/ppd/file-appeal/appeal-process or email PPDAppeals@portlandoregon.gov.
"""